AN EPIDEMIC OF UNCERTAINTY - THE CORONAVIRUS AND FORCE MAJEURE - WFW
Watson Farley  & WilliamsKNOWLEDGE TO ELEVATE

Do the effects of the coronavirus give rise to legitimate force majeure claims in connection with shipbuilding contracts (which similarly apply to offshore construction contracts), particularly those underway in China? In general terms, a force majeure event is an unforeseeable one that is outside a contracting party’s control and prevents that party from performing its contractual obligations.
 
“Frustration is invoked in fairly extreme circumstances and delay alone will not generally suffice.”
 
If a shipbuilding contract becomes impossible to perform, the builder may seek to invoke the English law doctrine of frustration, which exists independently of any contractual provisions. Frustration is invoked in fairly extreme circumstances and delay alone will not generally suffice. In contrast, under English law, for a force majeure claim to have any chance of success, there needs to be a force majeure clause in the contract. The scope of a force majeure claim is therefore limited to how it is defined in the contract.
 
TWO THRESHOLD CONSIDERATIONS FOR FORCE MAJEURE
The ability to make a valid claim of force majeure due to the coronavirus depends on two considerations:
 
- whether there is a force majeure clause in the shipbuilding contract that covers the effects of the coronavirus (the “qualification criteria”); and
- whether the coronavirus causes “critical delay” beyond the control of the builder that results in an entitlement to and extension of time (the “causation criteria”) – this would normally be demonstrated by a “critical path analysis” (discussed in greater detail below).
 
SATISFYING THE QUALIFICATION CRITERIA
Many shipbuilding contracts and standard form contracts (see below) contain force majeure clauses that arguably cover delays caused by the coronavirus or the government intervention policies that have been implemented to curb the outbreak.
 
For example, under the 2003 SAJ Form of shipbuilding contract, force majeure events include delays caused by “requirements of government authorities” and “labour shortage; plague or other epidemics; quarantines [and] embargoes”. Similarly, the NEWBUILDCON form of shipbuilding contracts refers to “epidemics” and “government requisition, control [and] intervention”. Some of these contracts contain a “sweeping-up” provision that may appear broad enough to cover such an outbreak.
 
However, despite the fact that (a) on a “plain English” reading, force majeure clauses arguably cover the coronavirus, (b) the World Health Organization (WHO) has declared the coronavirus a public health emergency of international concern and (c) the Chinese authorities have issued a number of “force majeure certificates”, none of these factors, whether taken in isolation or together, is likely to be sufficient to qualify the coronavirus as a force majeure event.
 
It remains uncertain whether these factors would be enough to meet the qualification criteria given that:
 
- the WHO declaration is arguably not proof, or evidence, per se, that a force majeure event has occurred;
- it is questionable whether the force majeure certificates issued by the Chinese authorities have force of law; and
- in view of the above, it is strongly arguable that an English law tribunal should not give significant evidentiary weight to either.
 
SATISFYING THE CAUSATION CRITERIA
In addition to satisfying the qualification criteria, a necessary component of any successful force majeure claim is satisfying the causation criteria. To do so, the builder would need to show that the force majeure event caused critical delay to the completion of the vessel, notwithstanding all reasonable attempts by the builder to avoid delay (i.e. the causation criteria).
 
By way of an example, we mention a case we recently handled where equipment in a yard was damaged during a typhoon and this (allegedly) caused delay to the construction of a series of ships. The yard referred to the force majeure provisions in the shipbuilding contracts which provided for typhoons as a force majeure event. However, we successfully argued that the damage to the equipment was caused by the failure to store it properly in advance of the typhoon striking. Thus, the “legal” (or proximate) cause of the delay was the failure to store properly, not the typhoon. The yard ultimately discontinued its force majeure claim and agreed to pay liquidated damages for late delivery.
 
Unprecedented measures have been taken by the Chinese government to control the spread of the coronavirus. These measures include mandatory quarantines, production bans and even city-wide lockdowns. Yards may seek to rely upon these as a basis to allege force majeure delay to construction schedules and supply chains, as employees are “prevented” from attending work. However, those yards will face possible counter arguments that a virus outbreak is not entirely unforeseeable, and builders should have taken measures to reduce or avoid the risks of business disruption in the event of an epidemic, given the painful experience from the SARS outbreak in 2003. It remains to be seen how courts or tribunals will view this, and each case will have to be considered on its merits. On balance, we believe that the coronavirus has the potential to cause more disruption than SARS, and it appears to be doing so. If this sad suspicion is realised, then force majeure claims will also likely increase, but whether or not such claims would succeed would very much depend on the facts of each claim.
 
CRITICAL PATH ANALYSIS
Assuming that the coronavirus does constitute a force majeure event causing “permissible delay” entitling the builder to an extension of time (“EOT”), that builder will still be required to demonstrate “causation” and thus be required to support its claim with adequate evidence. In a legal setting this means by documents and expert evidence. It is generally accepted nowadays, and advocated in the Society of Construction Law Delay and Disruption Protocol (2nd Edition 2017) (SCL Protocol), that the most acceptable method of proving delay in construction contracts is through a “critical path analysis” (“CPA”). A CPA details all the time-critical events leading up to a particular point, be it physical completion, the contractual completion date, or any interim period. Courts and tribunals now commonly accept CPAs as the best mechanism for presenting evidence of delay and its causes.
 
In practice, therefore, if a builder wishes to rely on an “epidemic” as the ground for a force majeure claim, it would need to show how the said epidemic itself caused the critical delay. This may require evidence of building programmes, employment records, medical records, manhour requirements, personnel attendance records, mitigation efforts or jobs complete reports, to name but a few types of document. A general reference to the coronavirus and its effects will probably be insufficient. A tribunal is not likely to accept secondary evidence, such as force majeure certificates issued by the Chinese authorities, as determinative.
 
“On top of the coronavirus, there may be a pre-existing or concurrent delay attributable to the negligence or breach by the builder, which is not uncommon in the shipbuilding industry.”
 
FORCE MAJEURE AND EXISTING DELAYS
The issue may be further complicated by the fact that, on top of the coronavirus, there may be a pre-existing or concurrent delay attributable to the negligence or breach by the builder (for example, materials used by the builder were found to be non-compliant with the planned specifications), which is not uncommon in the shipbuilding industry. In the case of the former, it may be open for the buyer to argue that, had the builder completed the contract and delivered the vessel as scheduled, production would not have been hampered by the subsequent coronavirus outbreak and therefore the builder should not be entitled to an EOT on the ground of force majeure. In contrast, for concurrent delays, authorities have indicated that where there are two concurrent causes of delay, one of which is a force majeure event and the other is not, the contractor may still be entitled to an EOT for the period of delay caused by the force majeure event notwithstanding the concurrent effect of the other event[1]. This is consistent with the approach in the SCL Protocol. The exact effects of a prior or concurrent delaying event will, however, depend on the wording of the force majeure provision in question. Further, it should be noted that the award of an EOT may be granted on a contiguous basis, i.e. starting on the previous due date for completion, regardless of whether there is a time gap between the previous due date and the occurrence of the event qualifying for an EOT[2]. This may be an important point for the builder if the contract provides for progressive rates of liquidated damages in the event of delay, or if there is no liquidated damages regime at all (which is unlikely), in which case the builder’s liability for delay may be the actual loss suffered by the buyer as a result of the delay.
 
PRACTICAL STEPS
- Builders wishing to assert a force majeure claim should retain documents in anticipation of claims being resisted.
- Conversely, buyers wishing to resist claims, should put builders to strict proof and not be intimidated by apparent compliance with the qualification criteria.
- Force majeure notice provisions should be strictly adhered to by builders. These will generally provide that notice of the force majeure event must be provided within a relatively short period of its occurrence (typically between 7 and 14 days). This may place yards in some difficulty if they are not able to identify when the claimed event occurred, and the delay started. It may be open to buyers to allege that notice periods have been missed, which generally results in permissible delay claims being vulnerable to challenge on the basis of time-bars.
- If buyers receive a force majeure notice, which is not accepted, this should be rejected within the relevant contractual timelines or the entitlement to defend the claim might be lost.
 
CONCLUSION
The social misery caused by the coronavirus looks set to continue for the time being, as do the legal problems that it is giving rise to. Parties to a shipbuilding contract should closely monitor the situation and seek professional legal advice to ascertain their contractual and common law rights when necessary.
Source: Watson Farley & Williams LLP


If you believe an article violates your rights or the rights of others, please contact us.

Recent News

Wednesday, 12 February 20
MARKET INSIGHT - INTERMODAL
The recent Coronavirus outbreak in China has led to a global health emergency by World Health Organization and it is yet to be seen how long the ph ...


Wednesday, 12 February 20
CHANGES IN LNG MARKET COULD UNDERCUT PLANS FOR NEW JAPANESE COAL PLANTS - CLYDE RUSSELL
Reuters: Clyde Russell   The collapse in the spot price of liquefied natural gas (LNG) in Asia is a short-term phenomenon that may wel ...


Wednesday, 12 February 20
THE SHIPPING INDUSTRY SEES FREIGHT MARKETS IN A COMPLETE STATE OF COLLAPSE AS DEMAND GETS PARALYZED DUE TO CORONAVIRUS OUTBREAK - ALLIED
With China and the world still trying to contain the effects and come to terms with the Wuhan novel coronavirus outbreak, the shipping industry see ...


Wednesday, 12 February 20
WORLD STEEL PRODUCTION IN 2019 - BANCHERO COSTA
In a worrying development, global steel production slowed down considerably in the fourth quarter of 2019. In the final 3 months of 2019, total cru ...


Sunday, 09 February 20
SUPRAMAX: THE ASIAN ARENA STRUGGLED, A 50,000DWT SHIP FIXING A COAL RUN FROM EAST KALIMANTAN TO INDIA AT $2,000 - THE BALTIC BRIEFING
Capesize The Capesize market endured another dreadful week of calamitous rate level falls, as the usual season low Q1 period combined with rece ...


   227 228 229 230 231   
Showing 1141 to 1145 news of total 6871
News by Category
Popular News
 
Total Members : 28,705
Member
Panelist
User ID
Password
Remember Me
By logging on you accept our TERMS OF USE.
Free
Register
Forgot Password
 
Our Members Are From ...

  • HSBC - Hong Kong
  • TNPL - India
  • Orica Mining Services - Indonesia
  • Pendopo Energi Batubara - Indonesia
  • White Energy Company Limited
  • MS Steel International - UAE
  • Australian Commodity Traders Exchange
  • India Bulls Power Limited - India
  • Miang Besar Coal Terminal - Indonesia
  • Petrochimia International Co. Ltd.- Taiwan
  • Enel Italy
  • Inco-Indonesia
  • Kohat Cement Company Ltd. - Pakistan
  • Intertek Mineral Services - Indonesia
  • GMR Energy Limited - India
  • KEPCO - South Korea
  • TRAFIGURA, South Korea
  • Dalmia Cement Bharat India
  • Surastha Cement
  • Rio Tinto Coal - Australia
  • Argus Media - Singapore
  • Billiton Holdings Pty Ltd - Australia
  • Indogreen Group - Indonesia
  • Ministry of Transport, Egypt
  • LBH Netherlands Bv - Netherlands
  • Mjunction Services Limited - India
  • Asia Cement - Taiwan
  • DBS Bank - Singapore
  • Tata Chemicals Ltd - India
  • Sakthi Sugars Limited - India
  • Economic Council, Georgia
  • Kalimantan Lumbung Energi - Indonesia
  • Mechel - Russia
  • Makarim & Taira - Indonesia
  • Jaiprakash Power Ventures ltd
  • Kaltim Prima Coal - Indonesia
  • Tanito Harum - Indonesia
  • Asia Pacific Energy Resources Ventures Inc, Philippines
  • WorleyParsons
  • Edison Trading Spa - Italy
  • Latin American Coal - Colombia
  • Globalindo Alam Lestari - Indonesia
  • Sinarmas Energy and Mining - Indonesia
  • Cardiff University - UK
  • Parry Sugars Refinery, India
  • UOB Asia (HK) Ltd
  • Africa Commodities Group - South Africa
  • Dr Ramakrishna Prasad Power Pvt Ltd - India
  • Coeclerici Indonesia
  • Kideco Jaya Agung - Indonesia
  • Global Coal Blending Company Limited - Australia
  • The University of Queensland
  • JPMorgan - India
  • GB Group - China
  • Gupta Coal India Ltd
  • Thermax Limited - India
  • Shenhua Group - China
  • Georgia Ports Authority, United States
  • Offshore Bulk Terminal Pte Ltd, Singapore
  • J M Baxi & Co - India
  • Straits Asia Resources Limited - Singapore
  • Thailand Anthracite
  • Toyota Tsusho Corporation, Japan
  • Permata Bank - Indonesia
  • Kobexindo Tractors - Indoneisa
  • Ministry of Mines - Canada
  • Chettinad Cement Corporation Ltd - India
  • ACC Limited - India
  • Indian Oil Corporation Limited
  • Coal and Oil Company - UAE
  • Indian School of Mines
  • IHS Mccloskey Coal Group - USA
  • Antam Resourcindo - Indonesia
  • Uttam Galva Steels Limited - India
  • U S Energy Resources
  • IEA Clean Coal Centre - UK
  • Riau Bara Harum - Indonesia
  • Adaro Indonesia
  • Coastal Gujarat Power Limited - India
  • Kobe Steel Ltd - Japan
  • Kapuas Tunggal Persada - Indonesia
  • Deloitte Consulting - India
  • Neyveli Lignite Corporation Ltd, - India
  • Gujarat Mineral Development Corp Ltd - India
  • PNOC Exploration Corporation - Philippines
  • Ernst & Young Pvt. Ltd.
  • Power Finance Corporation Ltd., India
  • Goldman Sachs - Singapore
  • Directorate General of MIneral and Coal - Indonesia
  • PetroVietnam Power Coal Import and Supply Company
  • Parliament of New Zealand
  • Pinang Coal Indonesia
  • Merrill Lynch Commodities Europe
  • Coal Orbis AG
  • Samsung - South Korea
  • Samtan Co., Ltd - South Korea
  • Freeport Indonesia
  • PTC India Limited - India
  • Asmin Koalindo Tuhup - Indonesia
  • Jatenergy - Australia
  • Carbofer General Trading SA - India
  • Platts
  • Cosco
  • Mitsubishi Corporation
  • Pipit Mutiara Jaya. PT, Indonesia
  • Interocean Group of Companies - India
  • Port Waratah Coal Services - Australia
  • Bhatia International Limited - India
  • Meralco Power Generation, Philippines
  • Ind-Barath Power Infra Limited - India
  • Ambuja Cements Ltd - India
  • Clarksons - UK
  • Anglo American - United Kingdom
  • CIMB Investment Bank - Malaysia
  • Maruti Cements - India
  • Siam City Cement - Thailand
  • Britmindo - Indonesia
  • Humpuss - Indonesia
  • South Luzon Thermal Energy Corporation
  • Renaissance Capital - South Africa
  • Chamber of Mines of South Africa
  • Maheswari Brothers Coal Limited - India
  • Krishnapatnam Port Company Ltd. - India
  • Salva Resources Pvt Ltd - India
  • bp singapore
  • Aboitiz Power Corporation - Philippines
  • KPCL - India
  • Aditya Birla Group - India
  • Romanian Commodities Exchange
  • Meenaskhi Energy Private Limited - India
  • Kepco SPC Power Corporation, Philippines
  • CESC Limited - India
  • Thiess Contractors Indonesia
  • Gujarat Sidhee Cement - India
  • McKinsey & Co - India
  • Japan Coal Energy Center
  • Core Mineral Indonesia
  • Lanco Infratech Ltd - India
  • Russian Coal LLC
  • ICICI Bank Limited - India
  • Total Coal South Africa
  • Xindia Steels Limited - India
  • Geoservices-GeoAssay Lab
  • Planning Commission, India
  • Videocon Industries ltd - India
  • Vedanta Resources Plc - India
  • Bahari Cakrawala Sebuku - Indonesia
  • Indian Energy Exchange, India
  • Asian Development Bank
  • Inspectorate - India
  • Alfred C Toepfer International GmbH - Germany
  • Metalloyd Limited - United Kingdom
  • Marubeni Corporation - India
  • Indonesia Power. PT
  • Malabar Cements Ltd - India
  • Sarangani Energy Corporation, Philippines
  • Iligan Light & Power Inc, Philippines
  • ING Bank NV - Singapore
  • The Treasury - Australian Government
  • Mitsui
  • Jindal Steel & Power Ltd - India
  • Formosa Plastics Group - Taiwan
  • CoalTek, United States
  • IOL Indonesia
  • Sindya Power Generating Company Private Ltd
  • ETA - Dubai
  • Coalindo Energy - Indonesia
  • Sucofindo - Indonesia
  • GHCL Limited - India
  • CCIC - Indonesia
  • Orica Australia Pty. Ltd.
  • Medco Energi Mining Internasional
  • OCBC - Singapore
  • Dong Bac Coal Mineral Investment Coporation - Vietnam
  • PLN Batubara - Indonesia
  • Karbindo Abesyapradhi - Indoneisa
  • OPG Power Generation Pvt Ltd - India
  • SN Aboitiz Power Inc, Philippines
  • Merrill Lynch Bank
  • globalCOAL - UK
  • GN Power Mariveles Coal Plant, Philippines
  • Cargill India Pvt Ltd
  • Bukit Baiduri Energy - Indonesia
  • European Bulk Services B.V. - Netherlands
  • Wilmar Investment Holdings
  • Noble Europe Ltd - UK
  • SMG Consultants - Indonesia
  • San Jose City I Power Corp, Philippines
  • SMC Global Power, Philippines
  • Indonesian Coal Mining Association
  • Electricity Generating Authority of Thailand
  • MEC Coal - Indonesia
  • Bukit Asam (Persero) Tbk - Indonesia
  • Thai Mozambique Logistica
  • Ceylon Electricity Board - Sri Lanka
  • SASOL - South Africa
  • Rashtriya Ispat Nigam Limited - India
  • Agrawal Coal Company - India
  • Global Business Power Corporation, Philippines
  • Maersk Broker
  • Maybank - Singapore
  • Moodys - Singapore
  • Platou - Singapore
  • Heidelberg Cement - Germany
  • Ministry of Finance - Indonesia
  • Holcim Trading Pte Ltd - Singapore
  • TNB Fuel Sdn Bhd - Malaysia
  • Shree Cement - India
  • Bhushan Steel Limited - India
  • Sree Jayajothi Cements Limited - India
  • Attock Cement Pakistan Limited
  • Energy Link Ltd, New Zealand
  • Wood Mackenzie - Singapore
  • Adani Power Ltd - India
  • International Coal Ventures Pvt Ltd - India
  • Qatrana Cement - Jordan
  • Berau Coal - Indonesia
  • Thomson Reuters GRC
  • Gujarat Electricity Regulatory Commission - India
  • Grasim Industreis Ltd - India
  • Energy Development Corp, Philippines
  • TeaM Sual Corporation - Philippines
  • Rudhra Energy - India
  • GVK Power & Infra Limited - India
  • Arutmin Indonesia
  • PetroVietnam
  • World Coal - UK
  • Bank of China, Malaysia
  • Credit Suisse - India
  • Jorong Barutama Greston.PT - Indonesia
  • PLN - Indonesia
  • Bharathi Cement Corporation - India
  • Indorama - Singapore
  • NALCO India
  • Fearnleys - India
  • Petron Corporation, Philippines
  • Thriveni
  • The State Trading Corporation of India Ltd
  • CNBM International Corporation - China
  • APGENCO India
  • Baramulti Group, Indonesia
  • Global Green Power PLC Corporation, Philippines
  • Bangladesh Power Developement Board
  • Tamil Nadu electricity Board
  • TANGEDCO India
  • Vitol - Bahrain
  • World Bank
  • AsiaOL BioFuels Corp., Philippines
  • Petrosea - Indonesia
  • Cemex - Philippines
  • IBC Asia (S) Pte Ltd
  • KPMG - USA
  • Lafarge - France
  • Kumho Petrochemical, South Korea
  • Semirara Mining Corp, Philippines
  • Savvy Resources Ltd - HongKong
  • BRS Brokers - Singapore
  • KOWEPO - South Korea
  • IMC Shipping - Singapore
  • Australian Coal Association
  • Bhoruka Overseas - Indonesia
  • McConnell Dowell - Australia
  • Mintek Dendrill Indonesia
  • Central Electricity Authority - India
  • Glencore India Pvt. Ltd
  • Vale Mozambique
  • EIA - United States
  • TGV SRAAC LIMITED, India
  • SRK Consulting
  • Altura Mining Limited, Indonesia
  • Cement Manufacturers Association - India
  • Ince & co LLP
  • RBS Sempra - UK
  • BNP Paribas - Singapore
  • Singapore Mercantile Exchange
  • Electricity Authority, New Zealand
  • Bukit Makmur.PT - Indonesia
  • Arch Coal - USA
  • Mercuria Energy - Indonesia
  • Barasentosa Lestari - Indonesia
  • Star Paper Mills Limited - India
  • Eastern Energy - Thailand
  • Cigading International Bulk Terminal - Indonesia
  • Bayan Resources Tbk. - Indonesia
  • Infraline Energy - India
  • Siam City Cement PLC, Thailand
  • Tata Power - India
  • Coaltrans Conferences
  • London Commodity Brokers - England
  • Leighton Contractors Pty Ltd - Australia
  • Vizag Seaport Private Limited - India
  • VISA Power Limited - India
  • NTPC Limited - India
  • Trasteel International SA, Italy
  • Indika Energy - Indonesia
  • Runge Indonesia
  • SGS (Thailand) Limited
  • Directorate Of Revenue Intelligence - India
  • Reliance Power - India
  • PowerSource Philippines DevCo
  • Karaikal Port Pvt Ltd - India
  • Indo Tambangraya Megah - Indonesia
  • Bank of Tokyo Mitsubishi UFJ Ltd
  • Price Waterhouse Coopers - Russia
  • Mercator Lines Limited - India
  • Essar Steel Hazira Ltd - India
  • Larsen & Toubro Limited - India
  • Semirara Mining and Power Corporation, Philippines
  • Panama Canal Authority
  • Vijayanagar Sugar Pvt Ltd - India
  • Malco - India
  • Mitra SK Pvt Ltd - India
  • EMO - The Netherlands
  • Idemitsu - Japan
  • Truba Alam Manunggal Engineering.Tbk - Indonesia
  • GNFC Limited - India
  • Central Java Power - Indonesia
  • Standard Chartered Bank - UAE
  • Sojitz Corporation - Japan
  • Simpson Spence & Young - Indonesia
  • Binh Thuan Hamico - Vietnam
  • Barclays Capital - USA
  • ASAPP Information Group - India
  • SUEK AG - Indonesia
  • Eastern Coal Council - USA
  • Therma Luzon, Inc, Philippines
  • Bangkok Bank PCL
  • Cebu Energy, Philippines
  • Minerals Council of Australia
  • New Zealand Coal & Carbon
  • Deutsche Bank - India
  • Peabody Energy - USA
  • Independent Power Producers Association of India
  • Xstrata Coal
  • Kartika Selabumi Mining - Indonesia
  • Timah Investasi Mineral - Indoneisa
  • The India Cements Ltd
  • Posco Energy - South Korea
  • Commonwealth Bank - Australia
  • Bulk Trading Sa - Switzerland
  • UBS Singapore
  • Maharashtra Electricity Regulatory Commission - India
  • ANZ Bank - Australia
  • Bank of America
  • Gresik Semen - Indonesia
  • Manunggal Multi Energi - Indonesia
  • Sical Logistics Limited - India
  • Borneo Indobara - Indonesia
  • Madhucon Powers Ltd - India
  • Oldendorff Carriers - Singapore
  • GAC Shipping (India) Pvt Ltd
  • Filglen & Citicon Mining (HK) Ltd - Hong Kong
  • JPower - Japan
  • Coal India Limited
  • Banpu Public Company Limited - Thailand