AN EPIDEMIC OF UNCERTAINTY - THE CORONAVIRUS AND FORCE MAJEURE - WFW
Watson Farley  & WilliamsKNOWLEDGE TO ELEVATE

Do the effects of the coronavirus give rise to legitimate force majeure claims in connection with shipbuilding contracts (which similarly apply to offshore construction contracts), particularly those underway in China? In general terms, a force majeure event is an unforeseeable one that is outside a contracting party’s control and prevents that party from performing its contractual obligations.
 
“Frustration is invoked in fairly extreme circumstances and delay alone will not generally suffice.”
 
If a shipbuilding contract becomes impossible to perform, the builder may seek to invoke the English law doctrine of frustration, which exists independently of any contractual provisions. Frustration is invoked in fairly extreme circumstances and delay alone will not generally suffice. In contrast, under English law, for a force majeure claim to have any chance of success, there needs to be a force majeure clause in the contract. The scope of a force majeure claim is therefore limited to how it is defined in the contract.
 
TWO THRESHOLD CONSIDERATIONS FOR FORCE MAJEURE
The ability to make a valid claim of force majeure due to the coronavirus depends on two considerations:
 
- whether there is a force majeure clause in the shipbuilding contract that covers the effects of the coronavirus (the “qualification criteria”); and
- whether the coronavirus causes “critical delay” beyond the control of the builder that results in an entitlement to and extension of time (the “causation criteria”) – this would normally be demonstrated by a “critical path analysis” (discussed in greater detail below).
 
SATISFYING THE QUALIFICATION CRITERIA
Many shipbuilding contracts and standard form contracts (see below) contain force majeure clauses that arguably cover delays caused by the coronavirus or the government intervention policies that have been implemented to curb the outbreak.
 
For example, under the 2003 SAJ Form of shipbuilding contract, force majeure events include delays caused by “requirements of government authorities” and “labour shortage; plague or other epidemics; quarantines [and] embargoes”. Similarly, the NEWBUILDCON form of shipbuilding contracts refers to “epidemics” and “government requisition, control [and] intervention”. Some of these contracts contain a “sweeping-up” provision that may appear broad enough to cover such an outbreak.
 
However, despite the fact that (a) on a “plain English” reading, force majeure clauses arguably cover the coronavirus, (b) the World Health Organization (WHO) has declared the coronavirus a public health emergency of international concern and (c) the Chinese authorities have issued a number of “force majeure certificates”, none of these factors, whether taken in isolation or together, is likely to be sufficient to qualify the coronavirus as a force majeure event.
 
It remains uncertain whether these factors would be enough to meet the qualification criteria given that:
 
- the WHO declaration is arguably not proof, or evidence, per se, that a force majeure event has occurred;
- it is questionable whether the force majeure certificates issued by the Chinese authorities have force of law; and
- in view of the above, it is strongly arguable that an English law tribunal should not give significant evidentiary weight to either.
 
SATISFYING THE CAUSATION CRITERIA
In addition to satisfying the qualification criteria, a necessary component of any successful force majeure claim is satisfying the causation criteria. To do so, the builder would need to show that the force majeure event caused critical delay to the completion of the vessel, notwithstanding all reasonable attempts by the builder to avoid delay (i.e. the causation criteria).
 
By way of an example, we mention a case we recently handled where equipment in a yard was damaged during a typhoon and this (allegedly) caused delay to the construction of a series of ships. The yard referred to the force majeure provisions in the shipbuilding contracts which provided for typhoons as a force majeure event. However, we successfully argued that the damage to the equipment was caused by the failure to store it properly in advance of the typhoon striking. Thus, the “legal” (or proximate) cause of the delay was the failure to store properly, not the typhoon. The yard ultimately discontinued its force majeure claim and agreed to pay liquidated damages for late delivery.
 
Unprecedented measures have been taken by the Chinese government to control the spread of the coronavirus. These measures include mandatory quarantines, production bans and even city-wide lockdowns. Yards may seek to rely upon these as a basis to allege force majeure delay to construction schedules and supply chains, as employees are “prevented” from attending work. However, those yards will face possible counter arguments that a virus outbreak is not entirely unforeseeable, and builders should have taken measures to reduce or avoid the risks of business disruption in the event of an epidemic, given the painful experience from the SARS outbreak in 2003. It remains to be seen how courts or tribunals will view this, and each case will have to be considered on its merits. On balance, we believe that the coronavirus has the potential to cause more disruption than SARS, and it appears to be doing so. If this sad suspicion is realised, then force majeure claims will also likely increase, but whether or not such claims would succeed would very much depend on the facts of each claim.
 
CRITICAL PATH ANALYSIS
Assuming that the coronavirus does constitute a force majeure event causing “permissible delay” entitling the builder to an extension of time (“EOT”), that builder will still be required to demonstrate “causation” and thus be required to support its claim with adequate evidence. In a legal setting this means by documents and expert evidence. It is generally accepted nowadays, and advocated in the Society of Construction Law Delay and Disruption Protocol (2nd Edition 2017) (SCL Protocol), that the most acceptable method of proving delay in construction contracts is through a “critical path analysis” (“CPA”). A CPA details all the time-critical events leading up to a particular point, be it physical completion, the contractual completion date, or any interim period. Courts and tribunals now commonly accept CPAs as the best mechanism for presenting evidence of delay and its causes.
 
In practice, therefore, if a builder wishes to rely on an “epidemic” as the ground for a force majeure claim, it would need to show how the said epidemic itself caused the critical delay. This may require evidence of building programmes, employment records, medical records, manhour requirements, personnel attendance records, mitigation efforts or jobs complete reports, to name but a few types of document. A general reference to the coronavirus and its effects will probably be insufficient. A tribunal is not likely to accept secondary evidence, such as force majeure certificates issued by the Chinese authorities, as determinative.
 
“On top of the coronavirus, there may be a pre-existing or concurrent delay attributable to the negligence or breach by the builder, which is not uncommon in the shipbuilding industry.”
 
FORCE MAJEURE AND EXISTING DELAYS
The issue may be further complicated by the fact that, on top of the coronavirus, there may be a pre-existing or concurrent delay attributable to the negligence or breach by the builder (for example, materials used by the builder were found to be non-compliant with the planned specifications), which is not uncommon in the shipbuilding industry. In the case of the former, it may be open for the buyer to argue that, had the builder completed the contract and delivered the vessel as scheduled, production would not have been hampered by the subsequent coronavirus outbreak and therefore the builder should not be entitled to an EOT on the ground of force majeure. In contrast, for concurrent delays, authorities have indicated that where there are two concurrent causes of delay, one of which is a force majeure event and the other is not, the contractor may still be entitled to an EOT for the period of delay caused by the force majeure event notwithstanding the concurrent effect of the other event[1]. This is consistent with the approach in the SCL Protocol. The exact effects of a prior or concurrent delaying event will, however, depend on the wording of the force majeure provision in question. Further, it should be noted that the award of an EOT may be granted on a contiguous basis, i.e. starting on the previous due date for completion, regardless of whether there is a time gap between the previous due date and the occurrence of the event qualifying for an EOT[2]. This may be an important point for the builder if the contract provides for progressive rates of liquidated damages in the event of delay, or if there is no liquidated damages regime at all (which is unlikely), in which case the builder’s liability for delay may be the actual loss suffered by the buyer as a result of the delay.
 
PRACTICAL STEPS
- Builders wishing to assert a force majeure claim should retain documents in anticipation of claims being resisted.
- Conversely, buyers wishing to resist claims, should put builders to strict proof and not be intimidated by apparent compliance with the qualification criteria.
- Force majeure notice provisions should be strictly adhered to by builders. These will generally provide that notice of the force majeure event must be provided within a relatively short period of its occurrence (typically between 7 and 14 days). This may place yards in some difficulty if they are not able to identify when the claimed event occurred, and the delay started. It may be open to buyers to allege that notice periods have been missed, which generally results in permissible delay claims being vulnerable to challenge on the basis of time-bars.
- If buyers receive a force majeure notice, which is not accepted, this should be rejected within the relevant contractual timelines or the entitlement to defend the claim might be lost.
 
CONCLUSION
The social misery caused by the coronavirus looks set to continue for the time being, as do the legal problems that it is giving rise to. Parties to a shipbuilding contract should closely monitor the situation and seek professional legal advice to ascertain their contractual and common law rights when necessary.
Source: Watson Farley & Williams LLP


If you believe an article violates your rights or the rights of others, please contact us.

Recent News

Saturday, 15 February 20
AFRAMAX: A MORE POSITIVE ATTITUDE EXISTED IN THIS SECTOR WITH RATES IMPROVING ON ALL ROUTES - BALTIC BRIEFING
VLCC The market in the Middle East was unmoved this week, with Chinese refiners continuing to slow imports, allied with the impact of the Coron ...


Saturday, 15 February 20
A 56,000DWT VESSEL WAS CONCLUDED BASIS DELIVERY SINGAPORE VIA INDONESIA REDELIVERY CHINA IN THE LOW $6,000S - BALTIC BRIEFING
Capesize Riding the downward momentum of the previous week, the market was always going to be hard pressed to make any sort of revival. With mu ...


Saturday, 15 February 20
U.S. COAL PRODUCTION WILL TOTAL 595 MMST IN 2020, DOWN 14% FROM 2019 - EIA
EIA forecasts that U.S. coal production will total 595 million short tons (MMst) in 2020, down 95 MMst (14%) from 2019.    Lower ...


Friday, 14 February 20
WHY THE WORLD ECONOMY WILL BE FACING CHINA'S CORONAVIRUS FOR A LONG TIME - CNBC
Everywhere we look we see the headlines and commentators talking about the coronavirus and its impact on tourism, trade and investment between Chin ...


Friday, 14 February 20
KOWEPO INVITED BIDS FOR 1.275 MILLION TONS OF MIN. 5,600 NCV COAL
COALspot.com: Korea Western Power Co. Ltd (KOWEPO). as a representative of five Korean Gencos has issued an international tender for total 1,275,00 ...


   225 226 227 228 229   
Showing 1131 to 1135 news of total 6871
News by Category
Popular News
 
Total Members : 28,705
Member
Panelist
User ID
Password
Remember Me
By logging on you accept our TERMS OF USE.
Free
Register
Forgot Password
 
Our Members Are From ...

  • PTC India Limited - India
  • GVK Power & Infra Limited - India
  • McKinsey & Co - India
  • Electricity Authority, New Zealand
  • Merrill Lynch Bank
  • Therma Luzon, Inc, Philippines
  • SUEK AG - Indonesia
  • Orica Mining Services - Indonesia
  • Deloitte Consulting - India
  • Dr Ramakrishna Prasad Power Pvt Ltd - India
  • Coal India Limited
  • Siam City Cement PLC, Thailand
  • Bank of China, Malaysia
  • Mechel - Russia
  • Edison Trading Spa - Italy
  • Lafarge - France
  • Ind-Barath Power Infra Limited - India
  • Central Java Power - Indonesia
  • Coal Orbis AG
  • Latin American Coal - Colombia
  • OPG Power Generation Pvt Ltd - India
  • Jindal Steel & Power Ltd - India
  • Indian Oil Corporation Limited
  • Planning Commission, India
  • Maharashtra Electricity Regulatory Commission - India
  • APGENCO India
  • Kaltim Prima Coal - Indonesia
  • Peabody Energy - USA
  • Arch Coal - USA
  • Infraline Energy - India
  • Dalmia Cement Bharat India
  • Runge Indonesia
  • Romanian Commodities Exchange
  • Tanito Harum - Indonesia
  • Global Green Power PLC Corporation, Philippines
  • Petrochimia International Co. Ltd.- Taiwan
  • ASAPP Information Group - India
  • Bhatia International Limited - India
  • Meralco Power Generation, Philippines
  • IBC Asia (S) Pte Ltd
  • IEA Clean Coal Centre - UK
  • HSBC - Hong Kong
  • Trasteel International SA, Italy
  • Vale Mozambique
  • KPMG - USA
  • New Zealand Coal & Carbon
  • Formosa Plastics Group - Taiwan
  • Offshore Bulk Terminal Pte Ltd, Singapore
  • Coal and Oil Company - UAE
  • Directorate Of Revenue Intelligence - India
  • KEPCO - South Korea
  • Idemitsu - Japan
  • Meenaskhi Energy Private Limited - India
  • Essar Steel Hazira Ltd - India
  • The Treasury - Australian Government
  • Deutsche Bank - India
  • Metalloyd Limited - United Kingdom
  • India Bulls Power Limited - India
  • Sarangani Energy Corporation, Philippines
  • Grasim Industreis Ltd - India
  • Ambuja Cements Ltd - India
  • Malco - India
  • TRAFIGURA, South Korea
  • Salva Resources Pvt Ltd - India
  • Total Coal South Africa
  • Coastal Gujarat Power Limited - India
  • Mitsui
  • Chettinad Cement Corporation Ltd - India
  • Truba Alam Manunggal Engineering.Tbk - Indonesia
  • Sojitz Corporation - Japan
  • Kepco SPC Power Corporation, Philippines
  • Indika Energy - Indonesia
  • Australian Commodity Traders Exchange
  • Ministry of Finance - Indonesia
  • Directorate General of MIneral and Coal - Indonesia
  • Gujarat Sidhee Cement - India
  • JPMorgan - India
  • Bangladesh Power Developement Board
  • Indogreen Group - Indonesia
  • Eastern Energy - Thailand
  • Renaissance Capital - South Africa
  • Miang Besar Coal Terminal - Indonesia
  • globalCOAL - UK
  • Core Mineral Indonesia
  • KOWEPO - South Korea
  • McConnell Dowell - Australia
  • Karbindo Abesyapradhi - Indoneisa
  • Bank of America
  • Cemex - Philippines
  • Rashtriya Ispat Nigam Limited - India
  • TANGEDCO India
  • Krishnapatnam Port Company Ltd. - India
  • Humpuss - Indonesia
  • International Coal Ventures Pvt Ltd - India
  • Globalindo Alam Lestari - Indonesia
  • Cebu Energy, Philippines
  • Pinang Coal Indonesia
  • Intertek Mineral Services - Indonesia
  • Indonesia Power. PT
  • Ceylon Electricity Board - Sri Lanka
  • bp singapore
  • Aboitiz Power Corporation - Philippines
  • Carbofer General Trading SA - India
  • CoalTek, United States
  • NTPC Limited - India
  • Malabar Cements Ltd - India
  • Pipit Mutiara Jaya. PT, Indonesia
  • Tamil Nadu electricity Board
  • Marubeni Corporation - India
  • LBH Netherlands Bv - Netherlands
  • CIMB Investment Bank - Malaysia
  • Coaltrans Conferences
  • PetroVietnam Power Coal Import and Supply Company
  • Indian Energy Exchange, India
  • Bukit Asam (Persero) Tbk - Indonesia
  • OCBC - Singapore
  • WorleyParsons
  • J M Baxi & Co - India
  • Antam Resourcindo - Indonesia
  • MEC Coal - Indonesia
  • Thermax Limited - India
  • Bukit Makmur.PT - Indonesia
  • TGV SRAAC LIMITED, India
  • Kideco Jaya Agung - Indonesia
  • Thriveni
  • Glencore India Pvt. Ltd
  • Maheswari Brothers Coal Limited - India
  • Sical Logistics Limited - India
  • Arutmin Indonesia
  • Indorama - Singapore
  • Savvy Resources Ltd - HongKong
  • Barclays Capital - USA
  • SGS (Thailand) Limited
  • Star Paper Mills Limited - India
  • GB Group - China
  • Inco-Indonesia
  • Standard Chartered Bank - UAE
  • Simpson Spence & Young - Indonesia
  • Commonwealth Bank - Australia
  • Lanco Infratech Ltd - India
  • Gujarat Electricity Regulatory Commission - India
  • Holcim Trading Pte Ltd - Singapore
  • PowerSource Philippines DevCo
  • Thiess Contractors Indonesia
  • European Bulk Services B.V. - Netherlands
  • Cargill India Pvt Ltd
  • Tata Power - India
  • RBS Sempra - UK
  • Binh Thuan Hamico - Vietnam
  • Uttam Galva Steels Limited - India
  • Chamber of Mines of South Africa
  • Reliance Power - India
  • Wilmar Investment Holdings
  • Ernst & Young Pvt. Ltd.
  • Energy Development Corp, Philippines
  • World Coal - UK
  • Thai Mozambique Logistica
  • The State Trading Corporation of India Ltd
  • Maersk Broker
  • Panama Canal Authority
  • Anglo American - United Kingdom
  • Gresik Semen - Indonesia
  • Jatenergy - Australia
  • CESC Limited - India
  • Africa Commodities Group - South Africa
  • Mercuria Energy - Indonesia
  • Jaiprakash Power Ventures ltd
  • Qatrana Cement - Jordan
  • Makarim & Taira - Indonesia
  • Alfred C Toepfer International GmbH - Germany
  • Argus Media - Singapore
  • Kartika Selabumi Mining - Indonesia
  • Electricity Generating Authority of Thailand
  • Moodys - Singapore
  • Credit Suisse - India
  • Geoservices-GeoAssay Lab
  • Russian Coal LLC
  • Dong Bac Coal Mineral Investment Coporation - Vietnam
  • Shenhua Group - China
  • Maybank - Singapore
  • Parliament of New Zealand
  • Iligan Light & Power Inc, Philippines
  • Fearnleys - India
  • San Jose City I Power Corp, Philippines
  • Samtan Co., Ltd - South Korea
  • BNP Paribas - Singapore
  • Power Finance Corporation Ltd., India
  • Sindya Power Generating Company Private Ltd
  • Price Waterhouse Coopers - Russia
  • Ince & co LLP
  • Vitol - Bahrain
  • Cosco
  • Vijayanagar Sugar Pvt Ltd - India
  • Gupta Coal India Ltd
  • Barasentosa Lestari - Indonesia
  • Singapore Mercantile Exchange
  • Gujarat Mineral Development Corp Ltd - India
  • Toyota Tsusho Corporation, Japan
  • White Energy Company Limited
  • GHCL Limited - India
  • Aditya Birla Group - India
  • GNFC Limited - India
  • Sree Jayajothi Cements Limited - India
  • NALCO India
  • Independent Power Producers Association of India
  • Interocean Group of Companies - India
  • CNBM International Corporation - China
  • TNB Fuel Sdn Bhd - Malaysia
  • Asia Pacific Energy Resources Ventures Inc, Philippines
  • GN Power Mariveles Coal Plant, Philippines
  • Semirara Mining Corp, Philippines
  • ING Bank NV - Singapore
  • TNPL - India
  • Australian Coal Association
  • Cigading International Bulk Terminal - Indonesia
  • Platou - Singapore
  • Asmin Koalindo Tuhup - Indonesia
  • Ministry of Mines - Canada
  • Semirara Mining and Power Corporation, Philippines
  • Bhoruka Overseas - Indonesia
  • Coeclerici Indonesia
  • Shree Cement - India
  • Bank of Tokyo Mitsubishi UFJ Ltd
  • JPower - Japan
  • Samsung - South Korea
  • South Luzon Thermal Energy Corporation
  • ETA - Dubai
  • Mitsubishi Corporation
  • Xindia Steels Limited - India
  • PetroVietnam
  • PNOC Exploration Corporation - Philippines
  • Xstrata Coal
  • Ministry of Transport, Egypt
  • EIA - United States
  • Borneo Indobara - Indonesia
  • London Commodity Brokers - England
  • Wood Mackenzie - Singapore
  • Heidelberg Cement - Germany
  • IOL Indonesia
  • Altura Mining Limited, Indonesia
  • BRS Brokers - Singapore
  • DBS Bank - Singapore
  • Freeport Indonesia
  • Vedanta Resources Plc - India
  • Bhushan Steel Limited - India
  • Sucofindo - Indonesia
  • Kobexindo Tractors - Indoneisa
  • Inspectorate - India
  • Global Coal Blending Company Limited - Australia
  • Indian School of Mines
  • Britmindo - Indonesia
  • CCIC - Indonesia
  • Filglen & Citicon Mining (HK) Ltd - Hong Kong
  • GMR Energy Limited - India
  • Mitra SK Pvt Ltd - India
  • Mintek Dendrill Indonesia
  • Billiton Holdings Pty Ltd - Australia
  • ICICI Bank Limited - India
  • IHS Mccloskey Coal Group - USA
  • Bulk Trading Sa - Switzerland
  • The University of Queensland
  • Coalindo Energy - Indonesia
  • Bahari Cakrawala Sebuku - Indonesia
  • Agrawal Coal Company - India
  • ANZ Bank - Australia
  • Kumho Petrochemical, South Korea
  • Platts
  • U S Energy Resources
  • Merrill Lynch Commodities Europe
  • Noble Europe Ltd - UK
  • PLN Batubara - Indonesia
  • Tata Chemicals Ltd - India
  • Bukit Baiduri Energy - Indonesia
  • Eastern Coal Council - USA
  • EMO - The Netherlands
  • VISA Power Limited - India
  • Minerals Council of Australia
  • Adani Power Ltd - India
  • PLN - Indonesia
  • Rudhra Energy - India
  • Adaro Indonesia
  • Straits Asia Resources Limited - Singapore
  • Cardiff University - UK
  • Neyveli Lignite Corporation Ltd, - India
  • Timah Investasi Mineral - Indoneisa
  • ACC Limited - India
  • Goldman Sachs - Singapore
  • AsiaOL BioFuels Corp., Philippines
  • KPCL - India
  • Sakthi Sugars Limited - India
  • UBS Singapore
  • SASOL - South Africa
  • Attock Cement Pakistan Limited
  • Oldendorff Carriers - Singapore
  • Japan Coal Energy Center
  • Jorong Barutama Greston.PT - Indonesia
  • The India Cements Ltd
  • Kapuas Tunggal Persada - Indonesia
  • Siam City Cement - Thailand
  • SMC Global Power, Philippines
  • Global Business Power Corporation, Philippines
  • Surastha Cement
  • Cement Manufacturers Association - India
  • Kohat Cement Company Ltd. - Pakistan
  • Kalimantan Lumbung Energi - Indonesia
  • World Bank
  • Orica Australia Pty. Ltd.
  • Baramulti Group, Indonesia
  • Enel Italy
  • Economic Council, Georgia
  • Parry Sugars Refinery, India
  • Petron Corporation, Philippines
  • Permata Bank - Indonesia
  • SRK Consulting
  • GAC Shipping (India) Pvt Ltd
  • Indo Tambangraya Megah - Indonesia
  • SMG Consultants - Indonesia
  • Port Waratah Coal Services - Australia
  • Posco Energy - South Korea
  • Mercator Lines Limited - India
  • Pendopo Energi Batubara - Indonesia
  • Manunggal Multi Energi - Indonesia
  • Thailand Anthracite
  • Mjunction Services Limited - India
  • Larsen & Toubro Limited - India
  • Clarksons - UK
  • Energy Link Ltd, New Zealand
  • Bangkok Bank PCL
  • Rio Tinto Coal - Australia
  • Bayan Resources Tbk. - Indonesia
  • Georgia Ports Authority, United States
  • Petrosea - Indonesia
  • Leighton Contractors Pty Ltd - Australia
  • Asian Development Bank
  • Central Electricity Authority - India
  • Madhucon Powers Ltd - India
  • Riau Bara Harum - Indonesia
  • Banpu Public Company Limited - Thailand
  • Asia Cement - Taiwan
  • Kobe Steel Ltd - Japan
  • Sinarmas Energy and Mining - Indonesia
  • Vizag Seaport Private Limited - India
  • Berau Coal - Indonesia
  • Videocon Industries ltd - India
  • Karaikal Port Pvt Ltd - India
  • Indonesian Coal Mining Association
  • TeaM Sual Corporation - Philippines
  • UOB Asia (HK) Ltd
  • SN Aboitiz Power Inc, Philippines
  • MS Steel International - UAE
  • IMC Shipping - Singapore
  • Thomson Reuters GRC
  • Bharathi Cement Corporation - India
  • Medco Energi Mining Internasional
  • Maruti Cements - India