AN EPIDEMIC OF UNCERTAINTY - THE CORONAVIRUS AND FORCE MAJEURE - WFW
Watson Farley  & WilliamsKNOWLEDGE TO ELEVATE

Do the effects of the coronavirus give rise to legitimate force majeure claims in connection with shipbuilding contracts (which similarly apply to offshore construction contracts), particularly those underway in China? In general terms, a force majeure event is an unforeseeable one that is outside a contracting party’s control and prevents that party from performing its contractual obligations.
 
“Frustration is invoked in fairly extreme circumstances and delay alone will not generally suffice.”
 
If a shipbuilding contract becomes impossible to perform, the builder may seek to invoke the English law doctrine of frustration, which exists independently of any contractual provisions. Frustration is invoked in fairly extreme circumstances and delay alone will not generally suffice. In contrast, under English law, for a force majeure claim to have any chance of success, there needs to be a force majeure clause in the contract. The scope of a force majeure claim is therefore limited to how it is defined in the contract.
 
TWO THRESHOLD CONSIDERATIONS FOR FORCE MAJEURE
The ability to make a valid claim of force majeure due to the coronavirus depends on two considerations:
 
- whether there is a force majeure clause in the shipbuilding contract that covers the effects of the coronavirus (the “qualification criteria”); and
- whether the coronavirus causes “critical delay” beyond the control of the builder that results in an entitlement to and extension of time (the “causation criteria”) – this would normally be demonstrated by a “critical path analysis” (discussed in greater detail below).
 
SATISFYING THE QUALIFICATION CRITERIA
Many shipbuilding contracts and standard form contracts (see below) contain force majeure clauses that arguably cover delays caused by the coronavirus or the government intervention policies that have been implemented to curb the outbreak.
 
For example, under the 2003 SAJ Form of shipbuilding contract, force majeure events include delays caused by “requirements of government authorities” and “labour shortage; plague or other epidemics; quarantines [and] embargoes”. Similarly, the NEWBUILDCON form of shipbuilding contracts refers to “epidemics” and “government requisition, control [and] intervention”. Some of these contracts contain a “sweeping-up” provision that may appear broad enough to cover such an outbreak.
 
However, despite the fact that (a) on a “plain English” reading, force majeure clauses arguably cover the coronavirus, (b) the World Health Organization (WHO) has declared the coronavirus a public health emergency of international concern and (c) the Chinese authorities have issued a number of “force majeure certificates”, none of these factors, whether taken in isolation or together, is likely to be sufficient to qualify the coronavirus as a force majeure event.
 
It remains uncertain whether these factors would be enough to meet the qualification criteria given that:
 
- the WHO declaration is arguably not proof, or evidence, per se, that a force majeure event has occurred;
- it is questionable whether the force majeure certificates issued by the Chinese authorities have force of law; and
- in view of the above, it is strongly arguable that an English law tribunal should not give significant evidentiary weight to either.
 
SATISFYING THE CAUSATION CRITERIA
In addition to satisfying the qualification criteria, a necessary component of any successful force majeure claim is satisfying the causation criteria. To do so, the builder would need to show that the force majeure event caused critical delay to the completion of the vessel, notwithstanding all reasonable attempts by the builder to avoid delay (i.e. the causation criteria).
 
By way of an example, we mention a case we recently handled where equipment in a yard was damaged during a typhoon and this (allegedly) caused delay to the construction of a series of ships. The yard referred to the force majeure provisions in the shipbuilding contracts which provided for typhoons as a force majeure event. However, we successfully argued that the damage to the equipment was caused by the failure to store it properly in advance of the typhoon striking. Thus, the “legal” (or proximate) cause of the delay was the failure to store properly, not the typhoon. The yard ultimately discontinued its force majeure claim and agreed to pay liquidated damages for late delivery.
 
Unprecedented measures have been taken by the Chinese government to control the spread of the coronavirus. These measures include mandatory quarantines, production bans and even city-wide lockdowns. Yards may seek to rely upon these as a basis to allege force majeure delay to construction schedules and supply chains, as employees are “prevented” from attending work. However, those yards will face possible counter arguments that a virus outbreak is not entirely unforeseeable, and builders should have taken measures to reduce or avoid the risks of business disruption in the event of an epidemic, given the painful experience from the SARS outbreak in 2003. It remains to be seen how courts or tribunals will view this, and each case will have to be considered on its merits. On balance, we believe that the coronavirus has the potential to cause more disruption than SARS, and it appears to be doing so. If this sad suspicion is realised, then force majeure claims will also likely increase, but whether or not such claims would succeed would very much depend on the facts of each claim.
 
CRITICAL PATH ANALYSIS
Assuming that the coronavirus does constitute a force majeure event causing “permissible delay” entitling the builder to an extension of time (“EOT”), that builder will still be required to demonstrate “causation” and thus be required to support its claim with adequate evidence. In a legal setting this means by documents and expert evidence. It is generally accepted nowadays, and advocated in the Society of Construction Law Delay and Disruption Protocol (2nd Edition 2017) (SCL Protocol), that the most acceptable method of proving delay in construction contracts is through a “critical path analysis” (“CPA”). A CPA details all the time-critical events leading up to a particular point, be it physical completion, the contractual completion date, or any interim period. Courts and tribunals now commonly accept CPAs as the best mechanism for presenting evidence of delay and its causes.
 
In practice, therefore, if a builder wishes to rely on an “epidemic” as the ground for a force majeure claim, it would need to show how the said epidemic itself caused the critical delay. This may require evidence of building programmes, employment records, medical records, manhour requirements, personnel attendance records, mitigation efforts or jobs complete reports, to name but a few types of document. A general reference to the coronavirus and its effects will probably be insufficient. A tribunal is not likely to accept secondary evidence, such as force majeure certificates issued by the Chinese authorities, as determinative.
 
“On top of the coronavirus, there may be a pre-existing or concurrent delay attributable to the negligence or breach by the builder, which is not uncommon in the shipbuilding industry.”
 
FORCE MAJEURE AND EXISTING DELAYS
The issue may be further complicated by the fact that, on top of the coronavirus, there may be a pre-existing or concurrent delay attributable to the negligence or breach by the builder (for example, materials used by the builder were found to be non-compliant with the planned specifications), which is not uncommon in the shipbuilding industry. In the case of the former, it may be open for the buyer to argue that, had the builder completed the contract and delivered the vessel as scheduled, production would not have been hampered by the subsequent coronavirus outbreak and therefore the builder should not be entitled to an EOT on the ground of force majeure. In contrast, for concurrent delays, authorities have indicated that where there are two concurrent causes of delay, one of which is a force majeure event and the other is not, the contractor may still be entitled to an EOT for the period of delay caused by the force majeure event notwithstanding the concurrent effect of the other event[1]. This is consistent with the approach in the SCL Protocol. The exact effects of a prior or concurrent delaying event will, however, depend on the wording of the force majeure provision in question. Further, it should be noted that the award of an EOT may be granted on a contiguous basis, i.e. starting on the previous due date for completion, regardless of whether there is a time gap between the previous due date and the occurrence of the event qualifying for an EOT[2]. This may be an important point for the builder if the contract provides for progressive rates of liquidated damages in the event of delay, or if there is no liquidated damages regime at all (which is unlikely), in which case the builder’s liability for delay may be the actual loss suffered by the buyer as a result of the delay.
 
PRACTICAL STEPS
- Builders wishing to assert a force majeure claim should retain documents in anticipation of claims being resisted.
- Conversely, buyers wishing to resist claims, should put builders to strict proof and not be intimidated by apparent compliance with the qualification criteria.
- Force majeure notice provisions should be strictly adhered to by builders. These will generally provide that notice of the force majeure event must be provided within a relatively short period of its occurrence (typically between 7 and 14 days). This may place yards in some difficulty if they are not able to identify when the claimed event occurred, and the delay started. It may be open to buyers to allege that notice periods have been missed, which generally results in permissible delay claims being vulnerable to challenge on the basis of time-bars.
- If buyers receive a force majeure notice, which is not accepted, this should be rejected within the relevant contractual timelines or the entitlement to defend the claim might be lost.
 
CONCLUSION
The social misery caused by the coronavirus looks set to continue for the time being, as do the legal problems that it is giving rise to. Parties to a shipbuilding contract should closely monitor the situation and seek professional legal advice to ascertain their contractual and common law rights when necessary.
Source: Watson Farley & Williams LLP


If you believe an article violates your rights or the rights of others, please contact us.

Recent News

Friday, 07 February 20
CIL LOOKING TO TAP NON-POWER SECTORS FOR INCREMENTAL COAL, PTI REPORTED
The miner is looking to ramp up production to meet its targets for the current fiscal at a time when the economic slowdown is impacting demand for ...


Friday, 07 February 20
VIRUS - HIT CHINA MAY NEED MORE IMPORTS OF COAL. NOW COMES THE TRICKY PART - SHIPPING IT THERE: REUTERS
China’s domestic coal mines are struggling to ramp up production in the face of the ongoing coronavirus epidemic. That’s a situation th ...


Friday, 07 February 20
CORONAVIRUS IMPACTING THE GLOBAL SHIPPING INDUSTRY - BIMCO
The outbreak of the novel Coronavirus has dented market sentiment and spooked markets around the globe. When China sneezes, we all catch the flu. T ...


Thursday, 06 February 20
CAPE: WEAK SUPPLY/DEMAND RATIO THE STREETS REMAIN BLOODY FOR THE BIG SHIPS - FEARNLEYS
Cape: With still a weak supply/demand ratio the streets remain bloody for the big ships, and actual spot earnings are close to zero on main short-h ...


Thursday, 06 February 20
CHINESE DEMAND KEY UNCERTAINTY FOR SEABORNE COAL MARKET IN 2020 - THE BRICS POST
Coal trader Noble Resources head of research Rodrigo Echeverri Cardozo had penciled in a 3 Mt drop in Chinese import demand for 2020, but it could ...


   228 229 230 231 232   
Showing 1146 to 1150 news of total 6871
News by Category
Popular News
 
Total Members : 28,705
Member
Panelist
User ID
Password
Remember Me
By logging on you accept our TERMS OF USE.
Free
Register
Forgot Password
 
Our Members Are From ...

  • Global Green Power PLC Corporation, Philippines
  • Mercator Lines Limited - India
  • Petron Corporation, Philippines
  • Directorate General of MIneral and Coal - Indonesia
  • Adani Power Ltd - India
  • JPower - Japan
  • Asia Cement - Taiwan
  • PTC India Limited - India
  • Kalimantan Lumbung Energi - Indonesia
  • KPMG - USA
  • Carbofer General Trading SA - India
  • Leighton Contractors Pty Ltd - Australia
  • Marubeni Corporation - India
  • LBH Netherlands Bv - Netherlands
  • Edison Trading Spa - Italy
  • London Commodity Brokers - England
  • Permata Bank - Indonesia
  • Central Java Power - Indonesia
  • Gupta Coal India Ltd
  • Larsen & Toubro Limited - India
  • IEA Clean Coal Centre - UK
  • Bulk Trading Sa - Switzerland
  • Indika Energy - Indonesia
  • Port Waratah Coal Services - Australia
  • San Jose City I Power Corp, Philippines
  • Simpson Spence & Young - Indonesia
  • Kobe Steel Ltd - Japan
  • Lanco Infratech Ltd - India
  • Arch Coal - USA
  • Parry Sugars Refinery, India
  • ASAPP Information Group - India
  • Britmindo - Indonesia
  • Vizag Seaport Private Limited - India
  • Energy Link Ltd, New Zealand
  • Infraline Energy - India
  • The Treasury - Australian Government
  • Intertek Mineral Services - Indonesia
  • Asia Pacific Energy Resources Ventures Inc, Philippines
  • Cigading International Bulk Terminal - Indonesia
  • TANGEDCO India
  • PLN Batubara - Indonesia
  • Thriveni
  • Sucofindo - Indonesia
  • Gujarat Mineral Development Corp Ltd - India
  • CIMB Investment Bank - Malaysia
  • Chettinad Cement Corporation Ltd - India
  • Maersk Broker
  • Panama Canal Authority
  • Rio Tinto Coal - Australia
  • Xstrata Coal
  • Idemitsu - Japan
  • Mitra SK Pvt Ltd - India
  • Kohat Cement Company Ltd. - Pakistan
  • Kartika Selabumi Mining - Indonesia
  • Australian Coal Association
  • Tata Chemicals Ltd - India
  • Sree Jayajothi Cements Limited - India
  • Ernst & Young Pvt. Ltd.
  • Bhatia International Limited - India
  • GVK Power & Infra Limited - India
  • Mechel - Russia
  • Romanian Commodities Exchange
  • Cement Manufacturers Association - India
  • Sical Logistics Limited - India
  • Star Paper Mills Limited - India
  • Jindal Steel & Power Ltd - India
  • Bhoruka Overseas - Indonesia
  • Bahari Cakrawala Sebuku - Indonesia
  • South Luzon Thermal Energy Corporation
  • IBC Asia (S) Pte Ltd
  • Indian Oil Corporation Limited
  • Barasentosa Lestari - Indonesia
  • Pipit Mutiara Jaya. PT, Indonesia
  • The India Cements Ltd
  • Coastal Gujarat Power Limited - India
  • Merrill Lynch Commodities Europe
  • Humpuss - Indonesia
  • Noble Europe Ltd - UK
  • Bharathi Cement Corporation - India
  • Xindia Steels Limited - India
  • bp singapore
  • Price Waterhouse Coopers - Russia
  • Jatenergy - Australia
  • Mercuria Energy - Indonesia
  • Samtan Co., Ltd - South Korea
  • Total Coal South Africa
  • Qatrana Cement - Jordan
  • Toyota Tsusho Corporation, Japan
  • U S Energy Resources
  • JPMorgan - India
  • Energy Development Corp, Philippines
  • Shenhua Group - China
  • Georgia Ports Authority, United States
  • Bangladesh Power Developement Board
  • Wood Mackenzie - Singapore
  • Filglen & Citicon Mining (HK) Ltd - Hong Kong
  • Economic Council, Georgia
  • APGENCO India
  • The State Trading Corporation of India Ltd
  • TNPL - India
  • Siam City Cement PLC, Thailand
  • Vale Mozambique
  • Cardiff University - UK
  • Ministry of Mines - Canada
  • GNFC Limited - India
  • World Coal - UK
  • Makarim & Taira - Indonesia
  • Coal India Limited
  • HSBC - Hong Kong
  • Orica Mining Services - Indonesia
  • Borneo Indobara - Indonesia
  • Karaikal Port Pvt Ltd - India
  • Coal Orbis AG
  • Latin American Coal - Colombia
  • Merrill Lynch Bank
  • European Bulk Services B.V. - Netherlands
  • Dong Bac Coal Mineral Investment Coporation - Vietnam
  • Tamil Nadu electricity Board
  • BRS Brokers - Singapore
  • Berau Coal - Indonesia
  • Kobexindo Tractors - Indoneisa
  • Cebu Energy, Philippines
  • Indian Energy Exchange, India
  • Thailand Anthracite
  • Semirara Mining Corp, Philippines
  • Surastha Cement
  • OCBC - Singapore
  • CNBM International Corporation - China
  • Clarksons - UK
  • ICICI Bank Limited - India
  • Glencore India Pvt. Ltd
  • ETA - Dubai
  • DBS Bank - Singapore
  • Maharashtra Electricity Regulatory Commission - India
  • Thomson Reuters GRC
  • Reliance Power - India
  • Asian Development Bank
  • PNOC Exploration Corporation - Philippines
  • Uttam Galva Steels Limited - India
  • Jaiprakash Power Ventures ltd
  • Manunggal Multi Energi - Indonesia
  • SMC Global Power, Philippines
  • Miang Besar Coal Terminal - Indonesia
  • PowerSource Philippines DevCo
  • Metalloyd Limited - United Kingdom
  • VISA Power Limited - India
  • Parliament of New Zealand
  • Dr Ramakrishna Prasad Power Pvt Ltd - India
  • EMO - The Netherlands
  • Commonwealth Bank - Australia
  • globalCOAL - UK
  • Sarangani Energy Corporation, Philippines
  • Australian Commodity Traders Exchange
  • Bukit Baiduri Energy - Indonesia
  • Minerals Council of Australia
  • ACC Limited - India
  • Inspectorate - India
  • Baramulti Group, Indonesia
  • Maybank - Singapore
  • Truba Alam Manunggal Engineering.Tbk - Indonesia
  • Enel Italy
  • Lafarge - France
  • Freeport Indonesia
  • Ince & co LLP
  • Aboitiz Power Corporation - Philippines
  • OPG Power Generation Pvt Ltd - India
  • Formosa Plastics Group - Taiwan
  • PetroVietnam Power Coal Import and Supply Company
  • Bhushan Steel Limited - India
  • SASOL - South Africa
  • KPCL - India
  • Meenaskhi Energy Private Limited - India
  • TGV SRAAC LIMITED, India
  • Posco Energy - South Korea
  • Mjunction Services Limited - India
  • Ministry of Transport, Egypt
  • Global Coal Blending Company Limited - Australia
  • Moodys - Singapore
  • NALCO India
  • International Coal Ventures Pvt Ltd - India
  • SN Aboitiz Power Inc, Philippines
  • Bank of Tokyo Mitsubishi UFJ Ltd
  • World Bank
  • Electricity Authority, New Zealand
  • Kaltim Prima Coal - Indonesia
  • Africa Commodities Group - South Africa
  • Vedanta Resources Plc - India
  • Coalindo Energy - Indonesia
  • Straits Asia Resources Limited - Singapore
  • Maheswari Brothers Coal Limited - India
  • Shree Cement - India
  • Offshore Bulk Terminal Pte Ltd, Singapore
  • Indonesia Power. PT
  • Iligan Light & Power Inc, Philippines
  • Petrochimia International Co. Ltd.- Taiwan
  • Pinang Coal Indonesia
  • Peabody Energy - USA
  • Tanito Harum - Indonesia
  • Core Mineral Indonesia
  • Vitol - Bahrain
  • Globalindo Alam Lestari - Indonesia
  • TeaM Sual Corporation - Philippines
  • Alfred C Toepfer International GmbH - Germany
  • Sinarmas Energy and Mining - Indonesia
  • ANZ Bank - Australia
  • Kapuas Tunggal Persada - Indonesia
  • J M Baxi & Co - India
  • PLN - Indonesia
  • Orica Australia Pty. Ltd.
  • Barclays Capital - USA
  • SGS (Thailand) Limited
  • Medco Energi Mining Internasional
  • Videocon Industries ltd - India
  • Mitsui
  • GMR Energy Limited - India
  • Samsung - South Korea
  • NTPC Limited - India
  • Dalmia Cement Bharat India
  • Semirara Mining and Power Corporation, Philippines
  • Bangkok Bank PCL
  • Malco - India
  • Attock Cement Pakistan Limited
  • Sakthi Sugars Limited - India
  • Sojitz Corporation - Japan
  • Arutmin Indonesia
  • Singapore Mercantile Exchange
  • RBS Sempra - UK
  • Directorate Of Revenue Intelligence - India
  • Gujarat Electricity Regulatory Commission - India
  • Petrosea - Indonesia
  • Indogreen Group - Indonesia
  • Coaltrans Conferences
  • Bank of America
  • Grasim Industreis Ltd - India
  • Heidelberg Cement - Germany
  • Credit Suisse - India
  • CCIC - Indonesia
  • MS Steel International - UAE
  • Coal and Oil Company - UAE
  • WorleyParsons
  • Eastern Energy - Thailand
  • Geoservices-GeoAssay Lab
  • Vijayanagar Sugar Pvt Ltd - India
  • Bukit Asam (Persero) Tbk - Indonesia
  • IHS Mccloskey Coal Group - USA
  • Riau Bara Harum - Indonesia
  • CoalTek, United States
  • GN Power Mariveles Coal Plant, Philippines
  • Cosco
  • Wilmar Investment Holdings
  • Chamber of Mines of South Africa
  • Central Electricity Authority - India
  • Rudhra Energy - India
  • Gujarat Sidhee Cement - India
  • UBS Singapore
  • KEPCO - South Korea
  • TRAFIGURA, South Korea
  • Inco-Indonesia
  • Antam Resourcindo - Indonesia
  • Krishnapatnam Port Company Ltd. - India
  • Altura Mining Limited, Indonesia
  • Argus Media - Singapore
  • Bank of China, Malaysia
  • Agrawal Coal Company - India
  • Goldman Sachs - Singapore
  • Neyveli Lignite Corporation Ltd, - India
  • TNB Fuel Sdn Bhd - Malaysia
  • Thiess Contractors Indonesia
  • Deutsche Bank - India
  • Interocean Group of Companies - India
  • India Bulls Power Limited - India
  • BNP Paribas - Singapore
  • Rashtriya Ispat Nigam Limited - India
  • Trasteel International SA, Italy
  • Renaissance Capital - South Africa
  • GB Group - China
  • Electricity Generating Authority of Thailand
  • Banpu Public Company Limited - Thailand
  • UOB Asia (HK) Ltd
  • SMG Consultants - Indonesia
  • Anglo American - United Kingdom
  • Essar Steel Hazira Ltd - India
  • Ministry of Finance - Indonesia
  • Holcim Trading Pte Ltd - Singapore
  • Eastern Coal Council - USA
  • McKinsey & Co - India
  • Timah Investasi Mineral - Indoneisa
  • McConnell Dowell - Australia
  • KOWEPO - South Korea
  • Planning Commission, India
  • Sindya Power Generating Company Private Ltd
  • Indonesian Coal Mining Association
  • Therma Luzon, Inc, Philippines
  • Bayan Resources Tbk. - Indonesia
  • Cemex - Philippines
  • GHCL Limited - India
  • Thermax Limited - India
  • Billiton Holdings Pty Ltd - Australia
  • Adaro Indonesia
  • Indorama - Singapore
  • Indian School of Mines
  • Standard Chartered Bank - UAE
  • Kumho Petrochemical, South Korea
  • White Energy Company Limited
  • GAC Shipping (India) Pvt Ltd
  • Coeclerici Indonesia
  • Thai Mozambique Logistica
  • Karbindo Abesyapradhi - Indoneisa
  • EIA - United States
  • Mitsubishi Corporation
  • Platou - Singapore
  • Mintek Dendrill Indonesia
  • New Zealand Coal & Carbon
  • Indo Tambangraya Megah - Indonesia
  • Tata Power - India
  • Platts
  • CESC Limited - India
  • Jorong Barutama Greston.PT - Indonesia
  • Power Finance Corporation Ltd., India
  • Binh Thuan Hamico - Vietnam
  • IMC Shipping - Singapore
  • Oldendorff Carriers - Singapore
  • Asmin Koalindo Tuhup - Indonesia
  • Malabar Cements Ltd - India
  • Bukit Makmur.PT - Indonesia
  • Salva Resources Pvt Ltd - India
  • Global Business Power Corporation, Philippines
  • PetroVietnam
  • Fearnleys - India
  • Ambuja Cements Ltd - India
  • Madhucon Powers Ltd - India
  • Kideco Jaya Agung - Indonesia
  • Kepco SPC Power Corporation, Philippines
  • Pendopo Energi Batubara - Indonesia
  • AsiaOL BioFuels Corp., Philippines
  • Ind-Barath Power Infra Limited - India
  • SRK Consulting
  • Deloitte Consulting - India
  • Independent Power Producers Association of India
  • Siam City Cement - Thailand
  • IOL Indonesia
  • Cargill India Pvt Ltd
  • Maruti Cements - India
  • Ceylon Electricity Board - Sri Lanka
  • SUEK AG - Indonesia
  • MEC Coal - Indonesia
  • Japan Coal Energy Center
  • ING Bank NV - Singapore
  • Aditya Birla Group - India
  • Savvy Resources Ltd - HongKong
  • Runge Indonesia
  • The University of Queensland
  • Gresik Semen - Indonesia
  • Russian Coal LLC
  • Meralco Power Generation, Philippines