LAY-UP AND RE-ACTIVATION REVISITED - GARD
GARDKNOWLEDGE TO ELEVATE

The COVID-19 pandemic has affected the maritime industry in previously unthinkable ways. Ports around the world are denying entry to certain vessels, travel restrictions have postponed crew changes, ships are taken out of service and crew have been laid off. These operational problems are forcing some owners and operators to consider placing vessels in lay-up.
 
Owner’s decision
Once a vessel owner has decided to lay up a vessel, several important decisions must be made. The most important decision is the duration of the lay-up, which will be critical for the type of lay-up selected. If the owner expects to be able to re-employ the vessel in the next twelve months, a hot (or warm) lay-up will be appropriate, with minimum crew on board to keep the machinery and equipment in operational running condition. If the lay-up is planned to last longer than a year, the owner will probably choose to go for a cold lay-up, which will reduce the daily running costs to the actual lay-up fee and watchkeeping.
 
Another important decision is where to lay up the vessel. Owners should obtain approval from local authorities, including information on worst-case weather conditions.
 
Risks related to lay-up
The fact that a vessel has been laid up does not eliminate the risk that a claim may be made by the assured against the insurer during the period the vessel is laid up. The risk after lay-up will depend on a number of factors.
 
Lay-up has two phases – the lay-up itself and the reactivation, including the trading period immediately after breaking lay-up. Each phase has a different risk profile.
 
During lay-up the following risk scenarios can arise:
 
• Risk of being struck by another vessel. Even if the laid-up vessel is without blame, the possibility of the other vessel limiting liability may result in significant unrecoverable costs.
• Risk of breaking moorings. Dragging of the anchor is the most frequent cause of grounding, and having vessels anchored close to the shoreline increases this risk.
• Fire onboard. Vessels laid up in groups next to each other (platooning), can result in cumulative damage. A fire on board one vessel is dangerous but if moored next to other vessels it may spread to these also.
• Low security. Limited manning on board a laid-up and anchored vessel will make it more difficult to cope with emergency situations.
 
During reactivation or immediately after breaking lay-up the following may arise:
 
• Failures due to general deterioration of equipment. The atmosphere and especially the humidity may not have been monitored during lay-up, resulting in corrosion and deterioration.
• Failures due to corrosion inside piping systems and valves (hydraulic, pneumatic systems).
• Heavy machinery components sit statically in the same position or are turned with insufficient lubrication film.
• Starting up problems with malfunctioning regulators and control equipment.
• Failures because components have not been cleaned or opened up after months without operation.
• Electronic equipment start-up failures after months with no power and no software updates.
 
As far as insurance is concerned, lay-up constitutes an alteration of risk, since the vessel is taken out of the normal trade and the operation for which it was designed and equipped. Therefore, the owner (the assured) must inform his insurers that the vessel is taken out of service.
 
Impact on insurance
This first notice to the insurers will normally be followed by a request for a lay-up return of a portion of the premium, as a properly laid-up vessel may represent a reduced risk to insurers. Insurers will usually request additional information and evidence of safe lay-up, as the full risk picture can only be ascertained if there is total transparency between the parties.
 
It is a condition for P&I and hull and machinery insurances that the vessel maintains its Classification, either “in operation” or “laid up” status. A suspension of Class for any reason will automatically lead to a loss of insurance, and the insurance will not be reinstated without written confirmation from Class.
 
The impact of lay-up on the P&I cover is relatively easy to identify as the cargo, passengers and parts of the crew risks are removed or altered. The obvious remaining P&I risks will be possible pollution from leakages (fuel, lube, garbage, etc.) and in worst case a wreck removal if a vessel should break moorings and end up on a beach. Gard’s P&I Rules contain relevant provisions related to survey (Rule 9) and returns of premium (Rule 22). A distinct subjectivity to pro rata reduction of premiums is a minimum of 30 days in lay-up.
 
The impact on the hull and machinery cover is more complex, as the risk profile changes. The Nordic Marine Insurance Plan defines lay-up as an alteration of risk (§3-26) and requires that a lay-up plan is drawn up and submitted to the hull and machinery insurer for approval.
 
Upon receipt of a notice of lay-up Gard will request the following:
 
• Confirmation from owners that the vessel’s Class will be maintained.
• The lay-up plan.
 
The lay-up plan
The lay-up plan shall include requirements from Classification societies and describe how the vessel is laid-up and how it will be preserved and maintained during lay-up. The lay-up plan should also describe the reactivation procedures as foreseen, but obviously these must be modified according to the length of the lay-up.
 
Most Classification societies and a number of marine consulting companies have issued guidelines and recommendations on lay-up of vessels. Classification societies may in addition offer technical services such as lay-up surveys and issue lay-up declarations on how the vessel is laid-up and preserved. These are additional services offered by most Classification societies’ consultancy services which the vessel owners have to pay for. These surveys and declarations are highly recommended, as they usually cover in detail all of Gard’s requirements for documentation of a lay-up for both hull and machinery and P&I covers.
 
Many vessel owners prefer to use their own resources to plan the lay-up and prepare the lay-up plan according to their experience and in-depth knowledge of their vessel. To assist vessel owners, Gard has specified some minimum requirements that should be included in the lay-up plan.
 
The main three requirements which vessel owners must comply with, are:
 
1. The lay-up site must be described with particular attention to the weather conditions and must be approved by the local authorities.
2. The mooring and anchoring arrangements must be approved by or through the vessel’s Classification society. A competent body may perform the calculations, but the approval should go through the Classification society.
3. The vessel owner should contact the manufacturers of the critical equipment on board and make sure maintenance, preservation and reactivation are done according to their recommendations. Preserving expensive accommodation areas on cruise vessels is also important.
 
There are other requirements, such as prevention of and protection from fire and flooding, but the three main requirements listed above ensure that the vessel is laid-up in a sufficiently safe area, the moorings are adequate for the site and expected weather conditions, and the vessel and its equipment are taken care of according to the manufacturers’ recommendations.
 
Reactivation after lay-up
It is not during the lay-up itself that incidents leading to insurance claims usually happen. The most problematic of the different processes involved in a lay-up, and the easiest to overlook or postpone with a view to cutting costs, is the reactivation. This process can take longer than preparing the vessel for lay-up, and the resources necessary not only from the shore management and crew, but also from external service engineers and shipyards with dry-docks, will be demanding. These services can be in high demand during an economic recovery, which normally is the moment vessel owners want the vessels back in service.
 
Gard strongly recommends reactivation after long periods in lay-up to be carried out with utmost care and in accordance with Class and equipment manufacturers’ recommendations. Not only should the machinery itself be carefully handled, but attention must be paid to the fuel and lube oil quality, including analysis if these have been stored on board during the lay-up.
 
When the vessel is reactivated, Class must perform any outstanding surveys together with a full check of the entire machinery installation. Depending on the duration of the lay-up, dry-docking, or at least a sea trial, must be performed. Normally a full Safety Management System audit must also be carried out. The scope of the required surveys will depend to a certain degree on the preservation and maintenance carried out before and during the lay-up. It is therefore very important that these measures are documented during the lay-up. In the event of an insurance claim at a later stage, such documentation will be important to demonstrate that the necessary precautions were taken in accordance with manufacturers’ recommendations.
 
Underwriters may include specific reactivation clauses as part of the cover during lay-up. The main requirement is, again, the involvement of Class and manufacturers, but a separate “additional machinery deductible” may be introduced for a limited time after breaking lay-up to cover the additional risks.
 
Recommendations
It is recommended that the assured notify the insurers early in the planning of an upcoming lay-up period for a vessel. Based on the information provided, the insurers will determine if the idle period will be considered a lay-up and to further consider if they will require a third-party review of the lay-up plan and arrangements.
 
Furthermore, the insurers should be advised as early as possible when a decision is made to reactivate the vessel, in order for the insurers to review to what extent a reactivation survey should be carried out and to allow for the involvement of the surveyor at an early stage of the reactivation and re-commissioning planning.
 
Minimum requirements to be included in a lay-up plan
 
1. Lay-up site
A description of the lay-up site must be provided with a particular focus on the local weather conditions. The lay-up site must also be approved by the local authorities. Lay-up in hurricane-affected and/or tropical areas must be the subject of particular considerations.
 
2. Mooring/anchoring arrangements
Description and maintenance routines of anchoring and mooring arrangements must be provided including distances to shore and to other vessels. The arrangements should preferably be approved by the vessel’s Classification society or by a consultant appointed by them, but other competent bodies may also be used.
 
Information on seabed, maximum wind forces and direction, shore and on-board bollards, anchors with systems is needed for calculation purposes. The anchor windlasses and mooring winches which are in use or under constant tension must be the subject of frequent testing and maintenance to ensure that they function properly at all times.
 
3. Class status
Gard generally requires that the Class is changed into the status of “laid-up” to facilitate a return of premium. Annual and other mandatory surveys must be carried out in accordance with Class rules. As for vessels in normal trading it is a pre-requisite for cover that the Class rules and regulations are followed at all times also during the lay-up, and any suspension of Class will lead to termination of the insurance cover.
 
4. Minimum manning
The flag state’s requirement as to minimum number of crew for the different lay-up situations must be maintained. If watchmen and routine maintenance as described in the lay-up plan are contracted out to third parties, these arrangements must also be described in the lay-up plan.
 
5. Power availability
The lay-up plan should also include the envisaged need for propulsion power and describe the availability of tug assistance in the lay-up area.
 
6. Protection against explosions and fire
All cargo tanks, pump rooms, cofferdams and cargo lines must, as a general rule, be kept gas-free during lay-up. Inerted tanks may be acceptable if approved by local authorities. Hot work is only permitted if a valid gas-free certificate is kept on board.
 
All fire alarm systems must be fully operational during lay-up. The vessel’s normal fire-fighting systems must be available and ready for use. If fixed fire-fighting systems (CO2 tanks) are disconnected for any reason, substitute systems must be operational and approved by Class.
 
7. Precautions against flooding
All sea overboard valves not in use must be closed. If seawater coolers/condensers etc., are left open, the seawater connections must be blanked off.
 
The water level in the ballast tanks, pump room and bilges must be checked regularly and bilge alarm systems for all spaces must be maintained in normal operation. Temporary bilge alarm systems for cold lay-up conditions are acceptable. All watertight doors and manholes must be closed.
 
8. Maintenance of equipment
The lay-up plan must also include specific items in accordance with the manufacturers’ recommendations as to the preservation, maintenance and operation of machinery and other equipment to prevent damage occurring as a result of the items not being in normal use. The plan should describe the preservation and maintenance of among others:
 
• Main engine with turbocharger, gear and shafting arrangement
• Auxiliary engines with generators
• Boilers
• Rotating equipment such as pumps, compressors etc.
• Vessel type specific equipment
• General requirements as to ambient temperature and humidity, use of heaters, dehumidifiers, preservation oil, etc.
 
9. Resuming of trading/breaking of lay-up
The extent of survey and testing when breaking lay-up will depend on the extent of maintenance and other preservative measures which had been undertaken during the lay-up and the reason for breaking lay-up (trading, dry-dock for re-commissioning, scrap). Gard’s requirement is that Class’ requirements for re-commissioning are followed, and that the manufacturers’ recommendations for preservation and maintenance have been followed during the lay-up and re-commissioning.
Source: Gard


If you believe an article violates your rights or the rights of others, please contact us.

Recent News

Friday, 10 April 20
INDIA'S BULKS SUPPLY CHAIN TAKES A HIT DURING LOCKDOWN - WOOD MACKENZIE
India is under a three-week lockdown from 25 March to contain the spread of the coronavirus outbreak. Businesses are shut, and the supply chain is ...


Thursday, 09 April 20
SUSPENSION OF WRONGFUL TRADING IN LIGHT OF COVID 19 - WF&W
KNOWLEDGE TO ELEVATE DIRECTORS’ PERSONAL LIABILITY FOR WRONGFUL TRADING – RELIEF DURING THE CORONAVIRUS CRISIS As the UK&rsquo ...


Wednesday, 08 April 20
LESSONS LEARNED FROM SCRUBBER INSTALLATION AND OPERATION - ABS
KNOWLEDGE TO ELEVATE At the beginning of this year, the IMO’s global sulfur cap on marine fuels entered into force and shipowners who ch ...


Wednesday, 08 April 20
MARKET INSIGHT - INTERMODAL
With lockdown measures around the globe tightening during the last weeks of Q1, there is finally a feeling that most countries are slowly but stead ...


Tuesday, 07 April 20
SHIPPING MARKET ANALYSIS - ALLIED
With the first quarter of 2020 now firmly written in the books, it is worth examining what we have witnessed so far in the tanker market. Undoubted ...


   203 204 205 206 207   
Showing 1021 to 1025 news of total 6871
News by Category
Popular News
 
Total Members : 28,617
Member
Panelist
User ID
Password
Remember Me
By logging on you accept our TERMS OF USE.
Free
Register
Forgot Password
 
Our Members Are From ...

  • Ministry of Finance - Indonesia
  • Core Mineral Indonesia
  • Indo Tambangraya Megah - Indonesia
  • Semirara Mining Corp, Philippines
  • Ministry of Transport, Egypt
  • Thermax Limited - India
  • CCIC - Indonesia
  • Meralco Power Generation, Philippines
  • Credit Suisse - India
  • Japan Coal Energy Center
  • Salva Resources Pvt Ltd - India
  • Mitsui
  • Samtan Co., Ltd - South Korea
  • Global Coal Blending Company Limited - Australia
  • Karbindo Abesyapradhi - Indoneisa
  • Maersk Broker
  • Africa Commodities Group - South Africa
  • New Zealand Coal & Carbon
  • Tamil Nadu electricity Board
  • Attock Cement Pakistan Limited
  • Xstrata Coal
  • Mitsubishi Corporation
  • Romanian Commodities Exchange
  • Price Waterhouse Coopers - Russia
  • Petrosea - Indonesia
  • Parliament of New Zealand
  • Timah Investasi Mineral - Indoneisa
  • Carbofer General Trading SA - India
  • LBH Netherlands Bv - Netherlands
  • Iligan Light & Power Inc, Philippines
  • Indorama - Singapore
  • Tanito Harum - Indonesia
  • Straits Asia Resources Limited - Singapore
  • Rashtriya Ispat Nigam Limited - India
  • Kideco Jaya Agung - Indonesia
  • Videocon Industries ltd - India
  • Shenhua Group - China
  • Sree Jayajothi Cements Limited - India
  • Pinang Coal Indonesia
  • Posco Energy - South Korea
  • OCBC - Singapore
  • Aditya Birla Group - India
  • Wilmar Investment Holdings
  • Sucofindo - Indonesia
  • JPMorgan - India
  • Bangladesh Power Developement Board
  • GB Group - China
  • Thiess Contractors Indonesia
  • Goldman Sachs - Singapore
  • GNFC Limited - India
  • ASAPP Information Group - India
  • Marubeni Corporation - India
  • Altura Mining Limited, Indonesia
  • Interocean Group of Companies - India
  • Bulk Trading Sa - Switzerland
  • CESC Limited - India
  • Asmin Koalindo Tuhup - Indonesia
  • Makarim & Taira - Indonesia
  • MS Steel International - UAE
  • SMC Global Power, Philippines
  • Krishnapatnam Port Company Ltd. - India
  • Vizag Seaport Private Limited - India
  • KOWEPO - South Korea
  • Eastern Energy - Thailand
  • Bhoruka Overseas - Indonesia
  • Runge Indonesia
  • Asian Development Bank
  • Energy Development Corp, Philippines
  • Reliance Power - India
  • Edison Trading Spa - Italy
  • Antam Resourcindo - Indonesia
  • ING Bank NV - Singapore
  • Manunggal Multi Energi - Indonesia
  • Fearnleys - India
  • Humpuss - Indonesia
  • Bayan Resources Tbk. - Indonesia
  • IHS Mccloskey Coal Group - USA
  • Thailand Anthracite
  • Sakthi Sugars Limited - India
  • Kobe Steel Ltd - Japan
  • Enel Italy
  • Barasentosa Lestari - Indonesia
  • Qatrana Cement - Jordan
  • Miang Besar Coal Terminal - Indonesia
  • Coalindo Energy - Indonesia
  • Gresik Semen - Indonesia
  • Indian Oil Corporation Limited
  • PowerSource Philippines DevCo
  • Mjunction Services Limited - India
  • GAC Shipping (India) Pvt Ltd
  • OPG Power Generation Pvt Ltd - India
  • Semirara Mining and Power Corporation, Philippines
  • Chettinad Cement Corporation Ltd - India
  • ANZ Bank - Australia
  • Infraline Energy - India
  • Grasim Industreis Ltd - India
  • Australian Coal Association
  • Jindal Steel & Power Ltd - India
  • Karaikal Port Pvt Ltd - India
  • WorleyParsons
  • KPMG - USA
  • SUEK AG - Indonesia
  • bp singapore
  • Siam City Cement PLC, Thailand
  • Coeclerici Indonesia
  • Kalimantan Lumbung Energi - Indonesia
  • RBS Sempra - UK
  • Heidelberg Cement - Germany
  • Borneo Indobara - Indonesia
  • Bharathi Cement Corporation - India
  • Argus Media - Singapore
  • Sindya Power Generating Company Private Ltd
  • San Jose City I Power Corp, Philippines
  • White Energy Company Limited
  • SASOL - South Africa
  • Platts
  • DBS Bank - Singapore
  • Lanco Infratech Ltd - India
  • BRS Brokers - Singapore
  • PLN - Indonesia
  • ICICI Bank Limited - India
  • Kartika Selabumi Mining - Indonesia
  • PetroVietnam Power Coal Import and Supply Company
  • Berau Coal - Indonesia
  • Filglen & Citicon Mining (HK) Ltd - Hong Kong
  • European Bulk Services B.V. - Netherlands
  • Ambuja Cements Ltd - India
  • ETA - Dubai
  • Bank of Tokyo Mitsubishi UFJ Ltd
  • Chamber of Mines of South Africa
  • Electricity Generating Authority of Thailand
  • Orica Mining Services - Indonesia
  • BNP Paribas - Singapore
  • Ernst & Young Pvt. Ltd.
  • Siam City Cement - Thailand
  • Petrochimia International Co. Ltd.- Taiwan
  • Cardiff University - UK
  • Bhatia International Limited - India
  • Offshore Bulk Terminal Pte Ltd, Singapore
  • Jorong Barutama Greston.PT - Indonesia
  • Coal Orbis AG
  • The India Cements Ltd
  • Binh Thuan Hamico - Vietnam
  • Truba Alam Manunggal Engineering.Tbk - Indonesia
  • Malabar Cements Ltd - India
  • Coal India Limited
  • Petron Corporation, Philippines
  • Kumho Petrochemical, South Korea
  • Indonesia Power. PT
  • Jaiprakash Power Ventures ltd
  • Indonesian Coal Mining Association
  • SMG Consultants - Indonesia
  • International Coal Ventures Pvt Ltd - India
  • KEPCO - South Korea
  • Vale Mozambique
  • Madhucon Powers Ltd - India
  • PetroVietnam
  • Kapuas Tunggal Persada - Indonesia
  • Maheswari Brothers Coal Limited - India
  • AsiaOL BioFuels Corp., Philippines
  • Idemitsu - Japan
  • Central Electricity Authority - India
  • Cemex - Philippines
  • U S Energy Resources
  • Minerals Council of Australia
  • CIMB Investment Bank - Malaysia
  • Directorate General of MIneral and Coal - Indonesia
  • Baramulti Group, Indonesia
  • Coaltrans Conferences
  • Arch Coal - USA
  • Savvy Resources Ltd - HongKong
  • Merrill Lynch Bank
  • Billiton Holdings Pty Ltd - Australia
  • Cebu Energy, Philippines
  • Maharashtra Electricity Regulatory Commission - India
  • Adaro Indonesia
  • Inspectorate - India
  • Central Java Power - Indonesia
  • The University of Queensland
  • Holcim Trading Pte Ltd - Singapore
  • The Treasury - Australian Government
  • Jatenergy - Australia
  • IMC Shipping - Singapore
  • Oldendorff Carriers - Singapore
  • Essar Steel Hazira Ltd - India
  • TGV SRAAC LIMITED, India
  • Barclays Capital - USA
  • Deutsche Bank - India
  • UBS Singapore
  • Tata Chemicals Ltd - India
  • Eastern Coal Council - USA
  • Moodys - Singapore
  • APGENCO India
  • SGS (Thailand) Limited
  • Indian Energy Exchange, India
  • globalCOAL - UK
  • McKinsey & Co - India
  • Coastal Gujarat Power Limited - India
  • Ceylon Electricity Board - Sri Lanka
  • Mechel - Russia
  • Gujarat Electricity Regulatory Commission - India
  • IOL Indonesia
  • Bhushan Steel Limited - India
  • Alfred C Toepfer International GmbH - Germany
  • Parry Sugars Refinery, India
  • London Commodity Brokers - England
  • Ministry of Mines - Canada
  • Indika Energy - Indonesia
  • Tata Power - India
  • Electricity Authority, New Zealand
  • Vedanta Resources Plc - India
  • Power Finance Corporation Ltd., India
  • CNBM International Corporation - China
  • Independent Power Producers Association of India
  • Rudhra Energy - India
  • Britmindo - Indonesia
  • PLN Batubara - Indonesia
  • Sical Logistics Limited - India
  • Samsung - South Korea
  • Georgia Ports Authority, United States
  • Planning Commission, India
  • Rio Tinto Coal - Australia
  • Indian School of Mines
  • South Luzon Thermal Energy Corporation
  • Panama Canal Authority
  • Thai Mozambique Logistica
  • Mintek Dendrill Indonesia
  • Economic Council, Georgia
  • Coal and Oil Company - UAE
  • JPower - Japan
  • Sojitz Corporation - Japan
  • Dalmia Cement Bharat India
  • Kaltim Prima Coal - Indonesia
  • Maybank - Singapore
  • Ind-Barath Power Infra Limited - India
  • Permata Bank - Indonesia
  • Aboitiz Power Corporation - Philippines
  • PTC India Limited - India
  • Dong Bac Coal Mineral Investment Coporation - Vietnam
  • NTPC Limited - India
  • EIA - United States
  • Mercator Lines Limited - India
  • Kohat Cement Company Ltd. - Pakistan
  • Wood Mackenzie - Singapore
  • VISA Power Limited - India
  • Merrill Lynch Commodities Europe
  • Ince & co LLP
  • Vitol - Bahrain
  • Pipit Mutiara Jaya. PT, Indonesia
  • Malco - India
  • Global Green Power PLC Corporation, Philippines
  • Trasteel International SA, Italy
  • Bank of China, Malaysia
  • Globalindo Alam Lestari - Indonesia
  • Deloitte Consulting - India
  • Therma Luzon, Inc, Philippines
  • Global Business Power Corporation, Philippines
  • Freeport Indonesia
  • India Bulls Power Limited - India
  • Total Coal South Africa
  • TeaM Sual Corporation - Philippines
  • Gupta Coal India Ltd
  • Sinarmas Energy and Mining - Indonesia
  • TNPL - India
  • World Coal - UK
  • Cosco
  • HSBC - Hong Kong
  • Mercuria Energy - Indonesia
  • Energy Link Ltd, New Zealand
  • Pendopo Energi Batubara - Indonesia
  • Orica Australia Pty. Ltd.
  • KPCL - India
  • Kobexindo Tractors - Indoneisa
  • Noble Europe Ltd - UK
  • Vijayanagar Sugar Pvt Ltd - India
  • Surastha Cement
  • Formosa Plastics Group - Taiwan
  • Commonwealth Bank - Australia
  • Cement Manufacturers Association - India
  • Meenaskhi Energy Private Limited - India
  • Bukit Asam (Persero) Tbk - Indonesia
  • Star Paper Mills Limited - India
  • EMO - The Netherlands
  • Inco-Indonesia
  • PNOC Exploration Corporation - Philippines
  • CoalTek, United States
  • IBC Asia (S) Pte Ltd
  • Adani Power Ltd - India
  • Clarksons - UK
  • UOB Asia (HK) Ltd
  • Australian Commodity Traders Exchange
  • Asia Pacific Energy Resources Ventures Inc, Philippines
  • Shree Cement - India
  • Larsen & Toubro Limited - India
  • Indogreen Group - Indonesia
  • TRAFIGURA, South Korea
  • Bukit Makmur.PT - Indonesia
  • Bangkok Bank PCL
  • Mitra SK Pvt Ltd - India
  • Latin American Coal - Colombia
  • Xindia Steels Limited - India
  • Cigading International Bulk Terminal - Indonesia
  • Riau Bara Harum - Indonesia
  • Anglo American - United Kingdom
  • GMR Energy Limited - India
  • IEA Clean Coal Centre - UK
  • Simpson Spence & Young - Indonesia
  • Russian Coal LLC
  • The State Trading Corporation of India Ltd
  • NALCO India
  • Renaissance Capital - South Africa
  • Bahari Cakrawala Sebuku - Indonesia
  • Asia Cement - Taiwan
  • Glencore India Pvt. Ltd
  • Toyota Tsusho Corporation, Japan
  • Port Waratah Coal Services - Australia
  • SN Aboitiz Power Inc, Philippines
  • Medco Energi Mining Internasional
  • Bukit Baiduri Energy - Indonesia
  • Dr Ramakrishna Prasad Power Pvt Ltd - India
  • Maruti Cements - India
  • Agrawal Coal Company - India
  • Gujarat Sidhee Cement - India
  • Arutmin Indonesia
  • Metalloyd Limited - United Kingdom
  • Kepco SPC Power Corporation, Philippines
  • Directorate Of Revenue Intelligence - India
  • Singapore Mercantile Exchange
  • GHCL Limited - India
  • McConnell Dowell - Australia
  • SRK Consulting
  • Sarangani Energy Corporation, Philippines
  • MEC Coal - Indonesia
  • Cargill India Pvt Ltd
  • Gujarat Mineral Development Corp Ltd - India
  • GVK Power & Infra Limited - India
  • Standard Chartered Bank - UAE
  • J M Baxi & Co - India
  • World Bank
  • Thomson Reuters GRC
  • Bank of America
  • Lafarge - France
  • Neyveli Lignite Corporation Ltd, - India
  • Geoservices-GeoAssay Lab
  • Leighton Contractors Pty Ltd - Australia
  • ACC Limited - India
  • Banpu Public Company Limited - Thailand
  • TANGEDCO India
  • Platou - Singapore
  • Thriveni
  • Uttam Galva Steels Limited - India
  • Intertek Mineral Services - Indonesia
  • Peabody Energy - USA
  • GN Power Mariveles Coal Plant, Philippines
  • TNB Fuel Sdn Bhd - Malaysia