CAPITAL COSTS OF INDIAN COAL MINING PROJECT - AN ANALYST VIEW


By Mr Dipesh Dipu, Director - Consulting (Mining), Deloitte Touche Tohmatsu India Private Limited

The coal mining sector that has been opened partially through captive mining route has seen allocation of 208 coal blocks to private sector, government-owned power generation and other downstream companies. These coal blocks, however, have had limited success in terms of operationalisation on time and at budgeted costs. These have led to serious concerns for coal supplies for power generation sector in India.

One of the key concerns for the development of the coal mines in India has been the quantum of capital required which is the determinant of expected returns from investment perspective and the viability of the project in terms of affordability of power so generated. The capital costs for coal mining projects typically include costs of land, capital equipment and infrastructure to support mining and logistics. Project costs also include capitalised expenses for clearances and approvals that help the mining project take off.

Elements of Capital Costs
Cost of land typically means the cost of acquiring surface rights for coal bearing land for which allocation has been made by the appropriate authority. The recent social concerns that have generated a lot of debate in the country centre on the cost of land which the companies are willing to pay for acquiring surface rights. The recent trends indicate that the land values head northwards since the time of announcement of a project, which makes it challenging to estimate the cost of land. In states that have vast coal resources, the land acquisition issues have been observed to be acute. In Talcher and IB Valley coalfields of Orissa, for example, there are a large number of coal blocks proposed with massive capacities. In these coalfields, it may therefore be expected that land costs will be relatively higher for the coal mining projects. Costs of mining equipment largely dominate the project costs, although due to higher costs of land acquisitions, its proportions are likely to be revised downward. The costs of equipment, typically, are functions of geological characteristics, technology, mine design and requirement of coal processing. Equipment costs also include costs of electricity supply features, drainage systems, environmental management systems, surveillance systems and several others. The costs of construction of coal handling plants and railway siding are parts of support systems for evacuation of coal and if the coal project is relatively farther from the nearest railhead, the costs will be higher. For pit-head power project, the costs include the conveying system from mine to the coal handling system of the power project.

Key Determinants of Capital Costs
Technology is a key determinant of capital cost. Underground coal mining and surface (or opencast) mining has different requirements. In the underground mining methods, there are variants such as bord and pillar, longwall, shortwall and variants for thick seam mining such as horizontal slicing and inclined slicing; sub-level caving and others. The accesses to coal seams are made either through inclines (surface drifts) or vertical shafts, each of which may have substantially different capital cost. In surface mining methods, equipment selection largely determines the project costs - shovel-dumper combinations, dragline, bucket wheel excavators are mostly used in India. The geo-technical parameters like dip and strike length, inclination of seams, thickness of overburden layer, and stripping ratio are indicators of specifications of equipment required, which, in turn, indicate the capital costs.

Equipment selection, therefore, is at the core of the determination of capital costs. In surface mining, the equipment selection takes into account the geological features such as partings between coal seams and expected bench heights. These impact the selection of size of shovels and matching dumper sizes. In such cases, the natural economies of scale need not work and hence, the capital costs per tonne of production versus capacity or size of excavators is a non-linear function.

Apart from the excavators and hauling equipment, capital cost of surface mines also depend on size and number of drilling machines, which, in turn, are dependent on the hardness of the rock. For blasting, the use of site mix slurries or site mix emulsion explosives can eliminate the need to maintain a magazine at mine project and thus, lower the capital costs. Relatively softer rock formation, such as those of lignite, the drilling blasting processes may be replaced by continuous mining system as bucket wheel excavator. Rock fragmentation and the requirement of crushing (including secondary crushing and sizing) will determine the additional equipment required that have a direct bearing on capital costs.

Hydrological characteristics of mine indicate the requirement of drainage and pump capacities. These may be significant where the water tables are high and may have large capital costs required to keep the working faces prevented from being inundated.

Estimates
According to estimates, investments needed in surface coal mining in India are in the range of INR 1500-2100 (approximately US$ 31.65 - 44.30) per tonne of rated capacity. For example, investment in a one million tonne per annum capacity mine is expected to be INR 210 crore (approximately US$ 44.295 million). This estimation is based on a stripping ratio of 4:1 and appropriate adjustments can be made for projects that have higher or lower stripping ratios. This, however, is as good as only an estimate and for the purpose of evaluations and investment decision making purposes, nothing can substitute a detailed plan, including equipment selection and fleet size determination.

For underground mining, the estimates are in the range of INR 1900-2800 (approximately US$ 40.07 - 59.05) per tonne of rated capacity. These are estimated for project that are shallow (within 150 meters depth) and are worked with semi-mechanized bord and pillar mining methods.

Business models change contribution to capital costs
At a high level, project costs remain more or less unchanged, irrespective of ownerships and financing pattern. However, for the project developers, the project costs are not nearly as significant parameters as are the equity investments and returns thereof. The business models now being contemplated and implemented substantially reduces the equity investment and causes the owner of the coal mine to focus on alternative investments such as, those in power generation capacity building. Contract mining is fast catching up in India as the preferred mode for development and operations of mines. The business model of hiring contract mining companies for overburden removal and even mineral winning is not a recent innovation. There are a number of new projects being planned through contract routes. Even the traditional mining companies like, the Coal India Limited and SCCL have been contracting out their mining operations. The scope of work in many cases involves the contract mining company to use their own equipment to carry on mining activities, which reduces the capital expenditure requirement of the coal mine owner.

In a total outsourcing model, the owners contract out all the processes including statutory approvals and clearances, land acquisition, mine development and operations. The recently floated tenders of a few state government owned power utilities are proponents of this model. The prospective bidders for the contract mining projects are expected to conduct their own geo-technical assessments, study the feasibilities and bid for the long term contract. The owner pays for all of these as the coal is mined and delivered to the owner. This model reduces the capital expenditure required by the owner for the coal mine development to nearly negligible.

Other business model is that of equipment leasing, which reduces the initial capital cost substituting the same by a more manageable lease rentals. The finance and operating types of leases help the mining project to have substantially lower cash outflows at the beginning of the project and help match the revenues with the costs when the mine starts the production of coal.

Capital Cost Management
Costs form a part of the decision-making process and cannot be used as a stand-alone decision-making tool. For this reason, there are several frameworks that can be used as a decision-making tool for surface and underground mining projects. These frameworks incorporate thinking obtained from viewing costs as a holistic entity. Strategic Cost Management (SCM) provides the thinking behind viewing costs as a strategic issue. Life Cycle Costing (LCC) suggests making use of the Net Present Value (NPV) approach to account for the use of the capital equipment. The LCC approach incorporates a tool into the framework that ensures that the cost of technology (capital) is accounted for over its lifetime.

Costing is the processing of expenditures to calculate their cost to each project. A typical and an ideal cost management profile is given below:


As costs increase, performance gets impaired. When cost reduction is periodically initiated, it often results in a temporary cull of capabilities, directly impacting on future ability to deliver performance. Where cost reductions are achieved, performance often recovers temporarily, only for focus on proactive cost management to be lost, and for costs to begin to increase again. Without specific cost management action, this cycle can continue indefinitely.

It must be observed that the ability to influence project success and enhance value is greatest at the start of project evaluation and rapidly declines as a project advances towards implementation. In the same instance, the cost of change dramatically increases throughout each project evaluation stage. This suggests that the quality of the decision making in the early stages of project evaluation, primarily focused at capital costs, is critical to an optimal project outcome.

Cost Escalations and Indices
In coal mining projects, capital costs are dynamic and are inflated when the projects get delayed. Cost indexes provide a means of adjusting out-dated capital and operating cost information for the effects of inflation due to such delays. They are based on statistical averages of costs for specific items and time periods. There are the composite indexes for capital and operating costs for each of surface and underground coal mining and coal processing (preparation) operations, which are calculated taking into account several projects done in the past as well as taking economic indices into account. Indexes for specific cost centres, e.g., labour, equipment, transportation, fuel, explosives, tires, electric power, natural gas, and industrial chemicals are available, which are being used by the industry and the regulators to allow prudent escalations in the capital and the operating costs.

The above analysis was originally published on Infraline.

The views and opinions / conclusion expressed on this analysis is purely the writers’ own.

About Dipesh Dipu
Dipesh Dipu works as Director with Deloitte in the Energy and Resources consulting practice of the firm and anchors the Firm’s initiative in the mining and metals sectors. He is a mining engineering graduate from Indian School of Mines and is a Chartered Financial Analyst (CFA).

He has also done executive program in business management from Indian Institute of Management Calcutta. Dipesh has recently been awarded the Abheraj Baldota Gold Medal for the Young Mining Engineer of the Year 2007 by the Mining Engineers’ Association of India in recognition of his contributions in the improvement of mining industry in India.



If you believe an article violates your rights or the rights of others, please contact us.

Recent News

Thursday, 17 November 11
DRY BULK MARKET INCHES FORWARD AND INTO HIGHER GROUND - NIKOS ROUSSANOGLOU, HELLENIC SHIPPING
The dry bulk market edged higher yesterday, on the back of stronger demand for Capesize vessels and general improvement of sentiment on most of the ...


Thursday, 17 November 11
KOMIPO INVITES BIDS FOR 500K MT OF COAL
COALspot.com - Korea Midland Power Co. Ltd.(KOMIPO) is inviting bids for the supply of 500,000 Metric Tons of minimum 5700 kcal/kg coal of NAR bases ...


Thursday, 17 November 11
INDONESIAN GOVERNMENT PLANS TO ISSUE MORATORIUM ON COAL MINING LICENSE
COALspot.com - Energy and mineral resources ministry is plans to issue a moratorium on the issuance of coal mining licenses, after the anti-graft co ...


Wednesday, 16 November 11
KRISHNAPATNAM PORT BECOMES DEEPEST DRAFT PORT IN INDIA
COALspot.com - Krishnapatnam Port in its quest to be the best port in India has increased its draft to 17.5 meters, according to E-Mail statement fr ...


Wednesday, 16 November 11
CHINA'S INDONESIA COAL IMPORTS RISE IN OCTOBER
COALspot.com: Indonesia, the world largest coal exporter, shipped 31,162,688 MT of coal in October 2011. China was a largest importer of Indonesi ...


   994 995 996 997 998   
Showing 4976 to 4980 news of total 6871
News by Category
Popular News
 
Total Members : 28,622
Member
Panelist
User ID
Password
Remember Me
By logging on you accept our TERMS OF USE.
Free
Register
Forgot Password
 
Our Members Are From ...

  • Sojitz Corporation - Japan
  • Asian Development Bank
  • Mercuria Energy - Indonesia
  • Tata Chemicals Ltd - India
  • GNFC Limited - India
  • Indonesia Power. PT
  • Sucofindo - Indonesia
  • White Energy Company Limited
  • Argus Media - Singapore
  • Star Paper Mills Limited - India
  • Bhatia International Limited - India
  • Sindya Power Generating Company Private Ltd
  • Medco Energi Mining Internasional
  • ICICI Bank Limited - India
  • Holcim Trading Pte Ltd - Singapore
  • TNB Fuel Sdn Bhd - Malaysia
  • Enel Italy
  • GB Group - China
  • Arch Coal - USA
  • NTPC Limited - India
  • IMC Shipping - Singapore
  • IOL Indonesia
  • Rashtriya Ispat Nigam Limited - India
  • Tanito Harum - Indonesia
  • World Coal - UK
  • Clarksons - UK
  • Coalindo Energy - Indonesia
  • Maharashtra Electricity Regulatory Commission - India
  • Anglo American - United Kingdom
  • Vale Mozambique
  • Thai Mozambique Logistica
  • Kaltim Prima Coal - Indonesia
  • Indorama - Singapore
  • Arutmin Indonesia
  • Gujarat Electricity Regulatory Commission - India
  • Coal Orbis AG
  • Panama Canal Authority
  • Borneo Indobara - Indonesia
  • PowerSource Philippines DevCo
  • Cardiff University - UK
  • Bhushan Steel Limited - India
  • Asia Cement - Taiwan
  • Ernst & Young Pvt. Ltd.
  • ETA - Dubai
  • London Commodity Brokers - England
  • The Treasury - Australian Government
  • Adaro Indonesia
  • Heidelberg Cement - Germany
  • LBH Netherlands Bv - Netherlands
  • KOWEPO - South Korea
  • RBS Sempra - UK
  • Tamil Nadu electricity Board
  • Savvy Resources Ltd - HongKong
  • Central Java Power - Indonesia
  • Bangkok Bank PCL
  • Central Electricity Authority - India
  • Global Coal Blending Company Limited - Australia
  • Samtan Co., Ltd - South Korea
  • Kartika Selabumi Mining - Indonesia
  • J M Baxi & Co - India
  • Permata Bank - Indonesia
  • Peabody Energy - USA
  • Makarim & Taira - Indonesia
  • Bukit Asam (Persero) Tbk - Indonesia
  • SN Aboitiz Power Inc, Philippines
  • Gupta Coal India Ltd
  • CCIC - Indonesia
  • KEPCO - South Korea
  • Truba Alam Manunggal Engineering.Tbk - Indonesia
  • Directorate Of Revenue Intelligence - India
  • Rio Tinto Coal - Australia
  • World Bank
  • Xindia Steels Limited - India
  • Moodys - Singapore
  • The University of Queensland
  • Karaikal Port Pvt Ltd - India
  • International Coal Ventures Pvt Ltd - India
  • KPCL - India
  • Coastal Gujarat Power Limited - India
  • Georgia Ports Authority, United States
  • Bangladesh Power Developement Board
  • Electricity Authority, New Zealand
  • ING Bank NV - Singapore
  • JPMorgan - India
  • Formosa Plastics Group - Taiwan
  • Mercator Lines Limited - India
  • UOB Asia (HK) Ltd
  • Edison Trading Spa - Italy
  • McConnell Dowell - Australia
  • Toyota Tsusho Corporation, Japan
  • Meralco Power Generation, Philippines
  • Kideco Jaya Agung - Indonesia
  • Freeport Indonesia
  • PetroVietnam
  • Billiton Holdings Pty Ltd - Australia
  • Asia Pacific Energy Resources Ventures Inc, Philippines
  • GMR Energy Limited - India
  • CESC Limited - India
  • Pinang Coal Indonesia
  • Petrosea - Indonesia
  • Pendopo Energi Batubara - Indonesia
  • Madhucon Powers Ltd - India
  • Chamber of Mines of South Africa
  • Semirara Mining Corp, Philippines
  • SGS (Thailand) Limited
  • Cosco
  • Cigading International Bulk Terminal - Indonesia
  • Indika Energy - Indonesia
  • Maruti Cements - India
  • Noble Europe Ltd - UK
  • Inspectorate - India
  • Iligan Light & Power Inc, Philippines
  • Mitsubishi Corporation
  • Thermax Limited - India
  • ACC Limited - India
  • BNP Paribas - Singapore
  • Sree Jayajothi Cements Limited - India
  • EMO - The Netherlands
  • Filglen & Citicon Mining (HK) Ltd - Hong Kong
  • Antam Resourcindo - Indonesia
  • Thomson Reuters GRC
  • Banpu Public Company Limited - Thailand
  • Goldman Sachs - Singapore
  • GVK Power & Infra Limited - India
  • Runge Indonesia
  • GHCL Limited - India
  • Simpson Spence & Young - Indonesia
  • Asmin Koalindo Tuhup - Indonesia
  • Lafarge - France
  • Semirara Mining and Power Corporation, Philippines
  • NALCO India
  • Alfred C Toepfer International GmbH - Germany
  • Eastern Energy - Thailand
  • MEC Coal - Indonesia
  • Coaltrans Conferences
  • Global Business Power Corporation, Philippines
  • HSBC - Hong Kong
  • Petrochimia International Co. Ltd.- Taiwan
  • Qatrana Cement - Jordan
  • Merrill Lynch Commodities Europe
  • Cebu Energy, Philippines
  • Karbindo Abesyapradhi - Indoneisa
  • Maheswari Brothers Coal Limited - India
  • Platou - Singapore
  • Indian Energy Exchange, India
  • Barasentosa Lestari - Indonesia
  • Merrill Lynch Bank
  • Attock Cement Pakistan Limited
  • Binh Thuan Hamico - Vietnam
  • The State Trading Corporation of India Ltd
  • India Bulls Power Limited - India
  • Idemitsu - Japan
  • U S Energy Resources
  • Siam City Cement PLC, Thailand
  • Manunggal Multi Energi - Indonesia
  • Cement Manufacturers Association - India
  • Thailand Anthracite
  • Wood Mackenzie - Singapore
  • TGV SRAAC LIMITED, India
  • Bukit Makmur.PT - Indonesia
  • Ministry of Mines - Canada
  • Commonwealth Bank - Australia
  • Bahari Cakrawala Sebuku - Indonesia
  • Singapore Mercantile Exchange
  • ASAPP Information Group - India
  • Adani Power Ltd - India
  • Coal and Oil Company - UAE
  • Oldendorff Carriers - Singapore
  • Kumho Petrochemical, South Korea
  • Straits Asia Resources Limited - Singapore
  • Marubeni Corporation - India
  • European Bulk Services B.V. - Netherlands
  • DBS Bank - Singapore
  • Trasteel International SA, Italy
  • Samsung - South Korea
  • Aditya Birla Group - India
  • Credit Suisse - India
  • Power Finance Corporation Ltd., India
  • Bhoruka Overseas - Indonesia
  • Ministry of Transport, Egypt
  • Indo Tambangraya Megah - Indonesia
  • Ince & co LLP
  • Kobe Steel Ltd - Japan
  • Coal India Limited
  • Mitra SK Pvt Ltd - India
  • Offshore Bulk Terminal Pte Ltd, Singapore
  • Mechel - Russia
  • Bulk Trading Sa - Switzerland
  • Kepco SPC Power Corporation, Philippines
  • Vedanta Resources Plc - India
  • PetroVietnam Power Coal Import and Supply Company
  • VISA Power Limited - India
  • Cargill India Pvt Ltd
  • bp singapore
  • Inco-Indonesia
  • Maybank - Singapore
  • Sinarmas Energy and Mining - Indonesia
  • Dr Ramakrishna Prasad Power Pvt Ltd - India
  • Kohat Cement Company Ltd. - Pakistan
  • San Jose City I Power Corp, Philippines
  • Gresik Semen - Indonesia
  • Cemex - Philippines
  • EIA - United States
  • OCBC - Singapore
  • Platts
  • Bank of America
  • CNBM International Corporation - China
  • Gujarat Sidhee Cement - India
  • Berau Coal - Indonesia
  • Sarangani Energy Corporation, Philippines
  • Maersk Broker
  • MS Steel International - UAE
  • PTC India Limited - India
  • Russian Coal LLC
  • Grasim Industreis Ltd - India
  • SASOL - South Africa
  • Independent Power Producers Association of India
  • WorleyParsons
  • GAC Shipping (India) Pvt Ltd
  • Malco - India
  • OPG Power Generation Pvt Ltd - India
  • TANGEDCO India
  • Baramulti Group, Indonesia
  • Orica Australia Pty. Ltd.
  • SMC Global Power, Philippines
  • Timah Investasi Mineral - Indoneisa
  • Bank of China, Malaysia
  • Videocon Industries ltd - India
  • SRK Consulting
  • TNPL - India
  • Standard Chartered Bank - UAE
  • Humpuss - Indonesia
  • Neyveli Lignite Corporation Ltd, - India
  • McKinsey & Co - India
  • Uttam Galva Steels Limited - India
  • Core Mineral Indonesia
  • Ambuja Cements Ltd - India
  • Parliament of New Zealand
  • Electricity Generating Authority of Thailand
  • South Luzon Thermal Energy Corporation
  • Pipit Mutiara Jaya. PT, Indonesia
  • ANZ Bank - Australia
  • Energy Link Ltd, New Zealand
  • Deloitte Consulting - India
  • JPower - Japan
  • Port Waratah Coal Services - Australia
  • Japan Coal Energy Center
  • Mintek Dendrill Indonesia
  • Orica Mining Services - Indonesia
  • Surastha Cement
  • KPMG - USA
  • Energy Development Corp, Philippines
  • Krishnapatnam Port Company Ltd. - India
  • Mjunction Services Limited - India
  • Parry Sugars Refinery, India
  • TeaM Sual Corporation - Philippines
  • Larsen & Toubro Limited - India
  • Geoservices-GeoAssay Lab
  • TRAFIGURA, South Korea
  • Glencore India Pvt. Ltd
  • GN Power Mariveles Coal Plant, Philippines
  • Reliance Power - India
  • Salva Resources Pvt Ltd - India
  • Riau Bara Harum - Indonesia
  • Interocean Group of Companies - India
  • Britmindo - Indonesia
  • AsiaOL BioFuels Corp., Philippines
  • Jatenergy - Australia
  • Ceylon Electricity Board - Sri Lanka
  • Price Waterhouse Coopers - Russia
  • Ministry of Finance - Indonesia
  • BRS Brokers - Singapore
  • Leighton Contractors Pty Ltd - Australia
  • Vizag Seaport Private Limited - India
  • IEA Clean Coal Centre - UK
  • Global Green Power PLC Corporation, Philippines
  • Indian School of Mines
  • Shree Cement - India
  • Minerals Council of Australia
  • Jorong Barutama Greston.PT - Indonesia
  • Lanco Infratech Ltd - India
  • Intertek Mineral Services - Indonesia
  • Fearnleys - India
  • Renaissance Capital - South Africa
  • Ind-Barath Power Infra Limited - India
  • Vitol - Bahrain
  • APGENCO India
  • PLN Batubara - Indonesia
  • Xstrata Coal
  • Economic Council, Georgia
  • Globalindo Alam Lestari - Indonesia
  • Jindal Steel & Power Ltd - India
  • The India Cements Ltd
  • CoalTek, United States
  • Miang Besar Coal Terminal - Indonesia
  • IHS Mccloskey Coal Group - USA
  • Indonesian Coal Mining Association
  • New Zealand Coal & Carbon
  • Romanian Commodities Exchange
  • Total Coal South Africa
  • SMG Consultants - Indonesia
  • Wilmar Investment Holdings
  • Bukit Baiduri Energy - Indonesia
  • Kobexindo Tractors - Indoneisa
  • Vijayanagar Sugar Pvt Ltd - India
  • Chettinad Cement Corporation Ltd - India
  • Posco Energy - South Korea
  • Coeclerici Indonesia
  • Petron Corporation, Philippines
  • Agrawal Coal Company - India
  • Malabar Cements Ltd - India
  • Bank of Tokyo Mitsubishi UFJ Ltd
  • Africa Commodities Group - South Africa
  • Siam City Cement - Thailand
  • SUEK AG - Indonesia
  • Aboitiz Power Corporation - Philippines
  • Gujarat Mineral Development Corp Ltd - India
  • Barclays Capital - USA
  • Eastern Coal Council - USA
  • Dalmia Cement Bharat India
  • globalCOAL - UK
  • Dong Bac Coal Mineral Investment Coporation - Vietnam
  • PNOC Exploration Corporation - Philippines
  • Jaiprakash Power Ventures ltd
  • Australian Coal Association
  • Kalimantan Lumbung Energi - Indonesia
  • PLN - Indonesia
  • Indian Oil Corporation Limited
  • Indogreen Group - Indonesia
  • Latin American Coal - Colombia
  • Meenaskhi Energy Private Limited - India
  • Kapuas Tunggal Persada - Indonesia
  • Altura Mining Limited, Indonesia
  • Australian Commodity Traders Exchange
  • Mitsui
  • Directorate General of MIneral and Coal - Indonesia
  • Bayan Resources Tbk. - Indonesia
  • Bharathi Cement Corporation - India
  • Thriveni
  • Sakthi Sugars Limited - India
  • Thiess Contractors Indonesia
  • Planning Commission, India
  • Deutsche Bank - India
  • Infraline Energy - India
  • Sical Logistics Limited - India
  • Essar Steel Hazira Ltd - India
  • Metalloyd Limited - United Kingdom
  • Shenhua Group - China
  • Therma Luzon, Inc, Philippines
  • IBC Asia (S) Pte Ltd
  • UBS Singapore
  • Carbofer General Trading SA - India
  • CIMB Investment Bank - Malaysia
  • Rudhra Energy - India
  • Tata Power - India